Saturday, January 3, 2026

Happy New Year 2026! (JRL version)

Happy New Year! We hope that your 2026 will be a bright & incredible year for you. The team was rather busy through 2025, especially during the last few months of the year. We weren't able to compile a Snapshot feature to close the year off for updates on the Jurong Region Line (JRL), but will be working to make one happen for this month's progress. To make up for the lack of a Snapshot update though, here are some images that we've come across that may interest you.

Saturday, April 5, 2025

J102 - An update in Q1 2025

An overview of the 4 station sites under contract J102 as of end-Q1 2025.
Top (L - R) : JS1 - Choa Chu Kang (image by tan_yekai), JS2 - Choa Chu Kang West
Bottom (L - R) : JS2A - Forest Hill infill station, JS3 - Tengah

We're moving onto recapping the Q1 2025 progress of contract J102, awarded to Shanghai Tunnel Engineering Co. This contract of the Jurong Region Line (JRL) saw several key milestones being hit this past quarter, including but not limited to completion of viaduct segment launching, the commencement of roof frame installation works at the stations and the installation of escalators within the stations. We'll cover these in greater detail as we look at each station site closer.

Saturday, December 7, 2024

J102 / Choa Chu Kang, CCK West, Forest Hill & Tengah - A 2024 progress report

The stations of contract J102 in December 2024.

Continuing on with our 2024 progress report, we now come to the stations under contract J102. Arguably the largest contract under the Jurong Region Line (JRL), the contract stretches across approximately 4.3km from Choa Chu Kang to Tengah and includes 3 stations. Also included in the contract are the bare bones for a future station within Tengah's northeast sector, which we refer to as Forest Hill, after the Tengah planning district in which it is located.

Progress on the contract has seen several milestones through 2024 which include the handover of the first sections of viaduct to the track works contractor, completion of launch gantry Mulan's viaduct segment launching and the completion of all viaduct piers along the contract. We take a closer look at the various sections in detail after the jump.

Saturday, September 28, 2024

J102 - STEC update for Aug/Sep 2024

 

Today, contractor for package J102 - Shanghai Tunnel Engineering Co (STEC) - released a progress update on the package's official Telegram channel. The update features aerial views from a drone of the project's progress and all four stations (3 full build & 1 future infill) can be seen in the video. We'll go through some of the coverage from the video and accompanying update on upcoming works that was initially published, but subsequently retracted, as well.

Monday, September 9, 2024

J102 - New layout at Choa Chu Kang

 

8 September 2024 - A view of the station's Exit A with the partially relocated fareline in view.

7 September 2024 - Another view of the relocated fareline.

We earlier detailed the changes being made to Choa Chu Kang station. Over the past week or so, some of these changes to the existing station's concourse area have been changed. The existing fareline nearer to Exit C has been shifted further out towards Exit A. In addition, the new passenger service centre (PSC) for the North-South Line (NSL) has been put into service, with the old PSC being closed for service.

Thursday, July 25, 2024

J102 (Part 1) - Choa Chu Kang & Choa Chu Kang West update Q2 2024

 

24 June 2024 - A view of Choa Chu Kang & Choa Chu Kang West stations under contract J102
as of end-Q2.

A lot has taken place in Q2 for contract J102. With 4 stations being built under the contract, we had to split this update into 2 parts to make it more bite-sized and not an overload of information or more of a huge photo dump than it already is. Progress has been swift and moving full steam ahead as the changes to the sites can be seen with every visit. Nonetheless, it will still take some time before the Jurong Region Line (JRL) sections under this contract can achieve basic structural completion.

Tuesday, June 11, 2024

J102 - A deep dive into Choa Chu Kang's modifications

Graphical representation of the existing Choa Chu Kang North-South Line station concourse and
transfer mezzanine level before the Jurong Region Line expansion.

Graphical representation of the Choa Chu Kang station concourse & transfer mezzanine levels
after modification works for the Jurong Region Line.

There has been a lot of work going on at Choa Chu Kang station ahead of the Jurong Region Line (JRL)'s arrival in 2027. All these works will serve to allow the station to increase its capacity for handling commuter traffic. What are the works taking place and how will these help to increase the station's capacity you may ask? We're here to break it down so that you'll be able to better understand the ongoing works.

Modification works at Choa Chu Kang station entail the following:

  • Demolition of former Exit D & using this area for an expanded concourse fare paid area linking the North-South Line (NSL) & JRL
  • Construction of a second lift to serve the existing NSL platform
  • Addition of new mezzanine level on the northern side of the station to facilitate transfers between NSL & JRL
  • Demolition, replacement & reconfiguration of existing escalators & staircases connecting NSL concourse & platform levels
  • Expansion of existing mezzanine level on southern side of the station to facilitate transfers between NSL, JRL & BPLRT
  • Reconfiguration of existing fare gate layout from one fare line to 3 fare lines
  • Reconfiguration of circulation spaces within fare paid & fare unpaid areas of the NSL station concourse
  • Reconfiguration of retail outlets within NSL station
  • Relocation of passenger service centre for NSL station

Wednesday, March 27, 2024

J102 - Choa Chu Kang, Choa Chu Kang West, Forest Hill & Tengah update Q1 2024

 

18 March 2024 - An aerial view of the Choa Chu Kang station site.

18 March 2024 - An aerial view of the Choa Chu Kang West station.

18 March 2024 - Forest Hill / JS2A station at end Q1 2024.

18 March 2024 - A view of a partially obscured Tengah station, visible behind the launch gantry.
If you still have difficulty telling where the station is in the image, it is in front of the red and white
crane boom.

With Q1 of 2024 coming to a close soon, we're beginning our quarterly updates on the Jurong Region Line (JRL). Last week, we covered the progress of Tengah depot over the first quarter, including the commencement of trackworks! Today, we'll dive a little deeper into the works taking place under contract J102 by Shanghai Tunnel Engineering Co which includes 3 stations, approximately 4km of viaducts and a future shell station.

Sunday, October 29, 2023

J102 - Choa Chu Kang update Q3 2023

 

24 September 2023 - An overview of the station site at the end of Q3 2023.

Work over at Choa Chu Kang station has been barreling along with major progress made over the past quarter. Station columns have gone up and the viaduct piers parallel to the North-South Line (NSL) and Bukit Panjang LRT tracks have sprung up with crosshead construction beginning as well. Be warned, this post is going to be a long one and photo-heavy.

Tuesday, August 1, 2023

JRL PIC - Updated with new 3D station models

 

1 August 2023 - A view of the Choa Chu Kang station complex, which will feature 10 platforms
when completed - 4 for the LRT, 3 for the NSL & 3 for JRL.

A recent post by MP for Keat Hong divison, Mr. Zhulkarnain Abdul Rahim, showed a visit to the Jurong Region Line (JRL) Project Information Centre (PIC) featuring new station architectural models. Our team made a visit to the JRL PIC today to check out the new additions to the collection.

View more images after the jump.

Tuesday, July 18, 2023

J102 - Choa Chu Kang update Q2 2023

 

2 June 2023 - An aerial view of Choa Chu Kang Jurong Region Line (JRL) station work site.

23 March 2023 - A view of the station work site at the end of Q1 2023.

The past quarter has seen the station site at Choa Chu Kang take shape as rebar is installed and concrete poured. More of the station cable troughs and base slab can be seen being built. Installed rebar gives us an idea of where the facilities such as vertical transport and viaduct columns will go. Most of the work has progressed out of foundation works and will transit to the building of the station structure.

Wednesday, April 5, 2023

J102 - Choa Chu Kang update Q1 2023

 

23 March 2023 - An overview of the Choa Chu Kang JRL site.

Choa Chu Kang is going to be the station that connects it all - the Jurong Region Line (JRL), North-South Line (NSL) & Bukit Panjang LRT. Works have been on-going for a while now, when the site looked extremely different. Now a multi-storey carpark with commercial units on the ground floor has gone and the bus interchange has shifted to allow for the JRL construction. To say that the place looks different would be an understatement.

Saturday, March 4, 2023

The Six Stages to building an elevated MRT line - Preparatory Works (1)

 

We launched our new mini-series last week, a deep dive into the process of building an elevated MRT line which was last seen on the East-West Line when the Tuas West Extension was built. Join us as we explore the first of six distinct stages of bringing an elevated MRT line to life - the preparatory works stage.

Wednesday, February 22, 2023

J102 - Flythrough videos

Video by Juan Almighty

Recently we came across several render videos for contract J102. The first video shows the renders of Choa Chu Kang, Choa Chu Kang West & Tengah stations which are being built by contractor Shanghai Tunnel Engineering Co (STEC). Subsequent videos show the process of unloading components of the launch gantry at the storage site, assembly & lifting of the launch gantry used for viaduct construction and the construction of the base slab at Choa Chu Kang station.

Monday, December 12, 2022

J102 - Choa Chu Kang year-end update

 

10 December 2022 - An overview of the Choa Chu Kang station site.


The construction of Choa Chu Kang station involves the building of 2 new island platforms to serve the existing North-South Line (NSL) and the new Jurong Region Line (JRL). Work is underway to form the base of the station, which is likely to be one of the few 2-level stations sitting on the ground for the JRL. Most of the JRL stations will feature 2 levels, however the concourse levels should be elevated off street level necessitating the extra footing work before work can begin on the station levels proper.

Monday, September 5, 2022

J102 - Choa Chu Kang works progression

4 September 2022 - An aerial view of the station work site.

4 September 2022 - An aerial view of the station and approach track work
sites.

It has been a while since we've come to Choa Chu Kang and things are progressing fairly well. Foundation works are well under way at the station site where 2 new island platforms are being tacked on to the existing station for the Jurong Region Line (JRL) and to facilitate cross-platform transfers to the southbound North-South Line (NSL) track. Further along, work is also underway for the foundations of the piers towards Choa Chu Kang Avenue 3.

Sunday, August 21, 2022

JRL1 - Station renders

A view of Hong Kah station
Source: LTA & Eng Lee-Wai Fong JV

Recently we came across some new renders of the stations along the Jurong Region Line (JRL). We thought it would be fitting to do a re-post of all the renders we've amassed thus far. Do stay tuned as we'll let you know where we got the new renders from after the phase 3 batch.

Sunday, July 31, 2022

J102, J108 - Progress update

 

25 April 2022 - The beginnings of viaduct piers north of Choa Chu Kang station.

Its been a while since we caught up to how things are shaping up on the Jurong Region Line (JRL). Things are indeed picking up pace! We've made a few comparisons to how things looked in the past as far as possible. For this post in particular, we'll be covering the stations under contract J102 (Choa Chu Kang, Choa Chu Kang West & Tengah) and also Tengah Park under contract J108.

Tuesday, April 26, 2022

Choa Chu Kang - closure of exit D and shops

 

Cross section showing new additions under J102.
Source: LTA

Contract J102 was one of the first contracts awarded for the construction of the Jurong Region Line (JRL). As such, construction works at this contract are some of the farthest along. The contract entails the construction of 3 JRL stations, including addition & alteration works to the existing Choa Chu Kang station. To do this, a new platform will be added to allow for cross-platform transfer between the North South Line (NSL) and JRL. The concourse level will be expanded as well, to accommodate circulation and vertical access to the new platforms.

Friday, September 24, 2021

JRL1 Construction update - Q3 2021

8 September 2021 - A view of the Choa Chu Kang interchange site as seen from an MRT train.

It has been a few months since our last update and unfortunately, there has not been too much progress on the line's construction. Majority of the works are still focused on the preliminary stages of utility diversion and site preparation. At some sites, there has not been much visible progress while others show a bit more visible work. In this update we'll do our best to give an overall summary of the progress.