Saturday, June 6, 2026

JRL1 - A snapshot in May 2026

Overview of JRL Phase 1 stations JS1 - JS7 and JW1 - JW2 as of May 2026.
Top (L - R): JS1 - Choa Chu Kang, JS2 - Choa Chu Kang West, JS3 - Tengah
Middle (L - R): JS4 - Hong Kah, JS5 – Corporation, JS6 - Jurong West
Bottom (L - R): JS7 - Bahar Junction, JW1 - Gek Poh, JW2 - Tawas

Our last snapshot update for May 2026 cover phase 1 of the Jurong Region Line (JRL), since its been a while since we've checked in on progress there. With phase 1 due for opening in early 2028, the stations along this stretch are among the most advanced in construction phases. To date, 4 stations have been installed or are undergoing platform screen gate (PSG) installation. Track-related installation programme (TRIP) works are also in progress, covering noise barriers, signal installation and laying of electrical wiring along the viaducts. Find out more about the progress in 9 of the 10 stations after the jump.