J108 - Tengah Plantation update Q2 2023

 

14 May 2023 - A view of the concourse slab that has been cast.
Source: LinkedIn

Having cleared our updates on the quicker-moving phase 1 of the Jurong Region Line (JRL), we're now starting our updates on the 7 stations that will form phase 2 of the line. The first of these is the hardest to reach - Tengah Plantation - which is sited in the middle of Plantation Crescent in Tengah new town. There is good news though, as the area is set to open up from around August with the home owners receiving their keys shortly. This means that the area will gradually become accessible in addition to having several vantage points from which the construction can be observed. We'll definitely be making use of these to bring you some updates.


16 April2 2023 - A view of Tengah Plantation station.

16 April 2023

7 May 2023

7 May 2023

7 May 2023

14 May 2023 - Concourse level of Tengah Plantation station.
Source: LinkedIn

14 May 2023 - Another view of Tengah Plantation station at the concourse level.
Source: LinkedIn

20 May 2023 - One column of the portal pier visible in the road median.
Image by Alfred Yeo

20 May 2023 - A view of viaduct piers under construction ahead of Tengah Plantation station.
Image by Alfred Yeo

20 May 2023
Image by Alfred Yeo

20 May 2023
Image by Alfred Yeo


8 July 2023
Source: Amy Khor
15 July 2023 - A view of Tengah Plantation station and the progress of viaduct pier construction.

Over the past quarter, the viaduct piers on either side of the station have progressed significantly, with most of the columns reaching the crown level. The section to the north appears to have most of the piers cast, though work has not commenced on the crosshead construction as yet.

At the southern end, a few piers still remain between where the line veers off from Bukit Batok Road into Tengah estate. For the moment, the launching gantry "Magnificent Mammoth" has been taking a break after completing launching of the viaduct spans next to Tengah Park station. A portal pier needs to be constructed before works can continue launching the viaduct spans towards Tengah Plantation station.

With all this work still remaining, it will be an interesting opportunity to see the works up close once Tengah Plantation estate begins opening from next month onwards. Do stay tuned as we bring you more updates in time to come.

This post is also be available on Instagram & Facebook.