Phase 1
Tengah depot (Contract J101)
In a nutshell: The site is in various stages of construction - some parts have structures, some parts are beginning to have structures and other parts have piles. A lot of work still going on and even more to go before the facility is ready to receive the rolling stock next year.
|
16 September 2023 |
|
16 September 2023 |
|
16 September 2023 |
JS1 - Choa Chu Kang (Contract J102)
In a nutshell: Works are continuing on viaduct piers as well as the station. Reconfiguration works on the southern end of the North-South Line station concourse continue, with work also visible at the platform extension. This area is likely to be used for additional plant rooms while the concourse area houses more shops.
|
24 September 2023 |
|
24 September 2023 |
|
24 September 2023 |
|
24 September 2023 |
JS2 - Choa Chu Kang West (Contract J102)
In a nutshell: Casting works for the concourse slab crossheads have begun. More station piers are beginning to receive the same treatment, where scaffolding is being set up for concourse slab crosshead casting. Elsewhere, viaduct piers are also getting the crosshead treatment with several more now having the formwork being installed.
|
24 September 2023 |
|
24 September 2023 |
|
24 September 2023 |
JS2A - Forest Hill (Contract J102, provisional future station)
In a nutshell: This location is hard to see, but from what we can see, the trackbed or platform level appears to have some works being done.
|
24 September 2023 |
|
24 September 2023 |
JS3 - Tengah (Contract J102)
In a nutshell: Another tricky location to view, viaduct works are approaching the station from the south. The double-decked viaduct section is beginning to see progress.
|
16 September 2023 |
|
16 September 2023 |
JS4 - Hong Kah (Contract J103)
In a nutshell: It would appear that the ground/street-level columns are mostly completed now. Work has not yet begun on casting the concourse slab however.
|
1 September 2023 |
|
1 September 2023 |
JS5 - Corporation (Contract J103)
In a nutshell: Casting for the concourse slab is underway. Some viaduct segmental box girders have been launched while a launch gantry awaits installation.
|
16 September 2023 |
|
16 September 2023 |
|
16 September 2023 |
|
16 September 2023 |
JS6 - Jurong West (Contract J105)
In a nutshell: Viaduct works are progressing further west, away from the station site and making good progress. At the station, precast T-beams have been installed to form the concourse slab. One can easily make out where the elevators and escalators will be installed.
|
16 September 2023 |
|
16 September 2023 |
|
16 September 2023 |
|
16 September 2023 |
JS7 - Bahar Junction (Contract J105)
In a nutshell: Works are underway to begin construction of the portion of the station suspended over the road junction (Peng Kang Hill bound track & platform).
|
10 September 2023 |
|
10 September 2023 |
|
10 September 2023 |
|
10 September 2023 |
JS8 - Boon Lay (Contract J106)
In a nutshell: Several viaduct piers to the south will employ the use of precast segments for the crosshead construction. Work is underway for the first of several such piers.
|
10 September 2023 |
|
10 September 2023 |
|
10 September 2023 |
|
24 September 2023 |
JW1 - Gek Poh (Contract J107)
In a nutshell: The installation of precast concourse crosshead sections has begun.
|
28 September 2023 |
|
28 September 2023 |
|
28 September 2023 |
|
28 September 2023 |
JW2 - Tawas (Contract J107)
In a nutshell: Casting of the trackbed columns in the middle of the station at concourse level has begun.
|
24 September 2023 |
|
24 September 2023 |
Phase 2
JE1 - Tengah Plantation (Contract J108)
In a nutshell: Casting at the concourse level has begun and the shape of the station is becoming more apparent. Work on the viaduct piers entering Tengah from Bukit Batok Road has also progressed.
|
24 September 2023 |
|
24 September 2023 |
|
24 September 2023 |
|
24 September 2023 |
JE2 - Tengah Park (Contract J108)
In a nutshell: Work has begun on the beams that will connect the station columns together. Launch gantry Rocksteady, the second of 2 gantries for the contract, has begun work on its third viaduct span.
|
24 September 2023 |
|
24 September 2023 |
|
24 September 2023 |
|
24 September 2023 |
JE3 - Bukit Batok West (Contract J108)
In a nutshell: A new ramp has been put into use for access to a pedestrian overhead bridge above the Pan Island Expressway (PIE).
|
24 September 2023 |
|
24 September 2023 |
|
24 September 2023 |
|
24 September 2023 |
JE4 - Toh Guan (Contract J109)
In a nutshell: Foundation works continue along Jurong East Central. Some of the station pier bases are beginning to emerge.
|
24 September 2023 |
|
24 September 2023 |
|
24 September 2023 |
Tracks through Jurong East Integrated Transport Hub (Contract J120)
In a nutshell: With the three piers cast, work has commenced on the trestle that will be used to support viaduct segmental box girders during their installation.
|
17 September 2023 |
|
16 September 2023 |
JE5 - Jurong East (Contract J110)
In a nutshell: With the two outer rows of columns in place, work has begun for the third row which will be located closest to the existing station.
|
24 September 2023 |
|
24 September 2023 |
|
10 September 2023 |
JE6 - Jurong Town Hall (Contract J109)
In a nutshell: Both station and viaduct piers are beginning to emerge & climb upwards.
|
24 September 2023 |
|
24 September 2023 |
|
24 September 2023 |
|
24 September 2023 |
JE7 - Pandan Reservoir (Contract J107)
In a nutshell: The station site appears to be the same while foundation work goes on for the over run track that runs parallel to the reservoir.
|
1 September 2023 |
|
1 September 2023 |
|
24 September 2023 |
|
24 September 2023 |
Phase 3 (South)
JS9 - Enterprise (Contract J111)
In a nutshell: The first bases of 2 columns are beginning to emerge after casting of the pier caps.
|
28 September 2023 |
|
28 September 2023 |
|
28 September 2023 |
JS10 - Tukang (Contract J111)
In a nutshell: Preparations are underway for an upcoming road diversion which will create a suitable work site in the road median.
|
28 September 2023 |
|
28 September 2023 |
|
28 September 2023 |
JS11 - Jurong Hill (Contract J112)
In a nutshell: Work is underway for the creation of a work site in the current road median.
|
28 September 2023 |
|
28 September 2023 |
|
28 September 2023 |
JS12 - Jurong Pier (Contract J112)
In a nutshell: The first footings for the station columns have emerged.
|
28 September 2023 |
|
28 September 2023 |
|
28 September 2023 |
Phase 3 (North)
JW3 - Nanyang Gateway (Contract J113)
In a nutshell: Several viaduct piers are under construction. Bored piling continues at the station site.
|
16 September 2023 |
|
16 September 2023 |
|
16 September 2023 |
|
16 September 2023 |
JW4 - Nanyang Crescent (Contract J113)
In a nutshell: Several viaduct piers have been cast to the crown level. However, the slope where the station will be located still remains and has not been cut down yet.
|
16 September 2023 |
|
16 September 2023 |
|
16 September 2023 |
|
16 September 2023 |
JW5 - Peng Kang Hill (Contract J115A)
In a nutshell: This is probably the slowest among all stations in progress. The site has been cleared and site preparation is likely underway. There is no heavy machinery on site as yet.
|
16 September 2023 |
|
16 September 2023 |
|
16 September 2023 |
And with that, our September 2023 JRL snapshot is concluded. Do stay tuned as we will begin our Q3 updates pretty soon - next week in fact. So keep a look out for that dropping soon.