Friday, September 1, 2023

JRL - A snapshot in August 2023

Overview of JRL stations JS1 - JS8 as at end-July or August 2023.
Top (L - R): JS1 - Choa Chu Kang, JS2 - Choa Chu Kang West, JS2A - Forest Hill
Middle (L - R): JS3 - Tengah, JS4 - Hong Kah, JS5 - Corporation
Bottom (L - R): JS6 - Jurong West, JS7 - Bahar Junction, JS8 - Boon Lay

 
Overview of JRL stations JW1 - JW2 & JE1 - JE7 as at end-July or August 2023.
Top (L - R): JW1 - Gek Poh, JW2 - Tawas, JE1 - Tengah Plantation
Middle (L - R): JE2 - Tengah Park, JE3 - Bukit Batok West, JE4 - Toh Guan
Bottom (L - R): JE5 - Jurong East, JE6 - Jurong Town Hall, JE7 - Pandan Reservoir

Overview of JRL stations JS9 - JS12 as at end-July or August 2023.
Top (L - R): JS9 - Enterprise, JS10 - Tukang
Bottom (L - R): JS11 - Jurong Hill, JS12 - Jurong Pier

So we're going to try something new, given that we're aware our quarterly updates take extremely long and don't seem to be current enough. Here's a snapshot of the progress of the Jurong Region Line (JRL) stations under phases 1 and 2 as of end-July or August 2023. We'll try to see if we can do these for more current updates once a month to give you an idea of the latest progress, on top of the compiled quarterly progress updates.


Phase 1

Tengah Depot (Contract J101)
In a nutshell: Various works are taking place ranging from structural works to foundation works. The electrical substation is the most visible building structure at the moment.

31 August 2023

31 August 2023

31 August 2023

31 August 2023

31 August 2023

31 August 2023

31 August 2023


JS1 - Choa Chu Kang (Contract J102)
In a nutshell: Casting works are ongoing at the station for the columns that will support the new platform & trackbeds for the JRL. Some hoarding has gone up around the northern atrium at platform level to facilitate works taking place below.

13 August 2023

13 August 2023

13 August 2023

9 August 2023

13 August 2023


JS2 - Choa Chu Kang West (Contract J102)
In a nutshell: Structural works at various stages are taking place along Choa Chu Kang Avenue 3. Some of the station columns are being prepared for casting of the concourse level slab.

13 August 2023

13 August 2023

13 August 2023

13 August 2023


JS2A - Forest Hill (Contract J102, provisional future station)
In a nutshell: Station columns have been cast up to the platform level. It is expected that the station's concourse will be located at ground level on the road side table.

23 July 2023

23 July 2023


JS3 - Tengah (Contract J102)
In a nutshell: Very difficult to get a great view of this station until the flats at Tengah become accessible. On a best-guess basis, they should be working on the station structure at lower platform level.

23 July 2023

23 July 2023


JS4 - Hong Kah (Contract J103)
In a nutshell: Casting of station columns appears to be completed to the concourse level. The station will be located at the road side table but features an elevated concourse instead of a ground-level one.

27 August 2023

27 August 2023


JS5 - Corporation (Contract J103)
In a nutshell: Construction of the concourse slab is ongoing. A launch gantry appears to have been delivered to site and is being assembled for viaduct construction.

13 August 2023

13 August 2023

27 August 2023

27 August 2023

27 August 2023


JS6 - Jurong West (Contract J105)
In a nutshell: Work is ongoing to cast the cantilevered crossheads for the station piers. Further down, viaduct piers are at various stages of completion and viaduct segment launching works finally in full swing.

13 August 2023

13 August 2023

13 August 2023

13 August 2023


JS7 - Bahar Junction (Contract J105)
In a nutshell: Busy, busy month with the reconfiguration of the junction where the station will span across - the intersection of Jurong West Avenue 4 with Streets 64 & 75. Bored piling & construction of the station piers along Jurong West Avenue 4 (towards Avenue 2) is also underway.

13 August 2023

13 August 2023

13 August 2023

13 August 2023

13 August 2023

13 August 2023


JS8 - Boon Lay (Contract J106)
In a nutshell: Major works ongoing to construct the station structure both beneath and above the existing East-West Line (EWL) tracks. Further to the north, viaduct segment launching works are progressing smoothly with approximately 12 spans completed.

27 August 2023

27 August 2023

27 August 2023


JW1 - Gek Poh (Contract J107)
In a nutshell: Work is continuing on connecting the station piers together before launching of the precast crossheads for the concourse level. To the north, viaduct segment launching is in progress with approximately 2 spans completed. To the south, work is under way for the remaining viaduct piers.

30 July 2023

30 July 2023

30 July 2023

30 July 2023


JW2 - Tawas (Contract J107)
In a nutshell: Work is continuing on the station structure & viaduct piers.

17 August 2023


Phase 2

JE1 - Tengah Plantation (Contract J108)
In a nutshell: Works are progressing on the concourse level slab & columns. Casting of the pier crossheads is also taking place so that viaduct construction can be completed soon as residents will begin moving into the estate shortly.

6 August 2023

6 August 2023

6 August 2023

6 August 2023

6 August 2023


JE2 - Tengah Park (Contract J108)

In a nutshell: Station structure is slowly creeping upwards with most of the columns cast to the elevated concourse level. Recently, the second launch gantry has started work on launching viaduct segments at the cripple siding area south of the station structure.

6 August 2023

6 August 2023

6 August 2023

6 August 2023

27 August 2023


JE3 - Bukit Batok West (Contract J108)
In a nutshell: Viaduct piers near the contract boundary with J109 are beginning to take shape. Similarly, the footings for the station structure are beginning to emerge.

20 August 2023

20 August 2023

20 August 2023


JE4 - Toh Guan (Contract J109)
In a nutshell: Foundation works are in progress throughout the work sites.

13 August 2023

20 August 2023

20 August 2023

20 August 2023
31 August 2023


Tracks through Jurong East Integrated Transport Hub (Contract J120)
In a nutshell: 3 piers stand constructed. That's about all that can be said for the moment. The remaining areas are undergoing basement construction so it is unlikely that those piers will sprout up any time soon.

6 August 2023

6 August 2023

6 August 2023

6 August 2023


JE5 - Jurong East (Contract J110)
In a nutshell: Station columns are being cast progressively from west to east. Works have commenced to hoard up spaces at platform level for the construction of new plant rooms.

6 August 2023

6 August 2023

6 August 2023

6 August 2023

6 August 2023

6 August 2023


JE6 - Jurong Town Hall (Contract J109)
In a nutshell: The station structure is growing slightly with the service chambers being cast below the ground floor. A viaduct pier to the south is partially cast.

20 August 2023

20 August 2023

20 August 2023

20 August 2023


JE7 - Pandan Reservoir (Contract J107)
In a nutshell: Work is continuing along at the station site. The northern approach has shown signs of viaduct piers beginning to emerge. Work has commenced along West Coast Road parallel to the reservoir with bored piling for foundations underway.

20 August 2023

20 August 2023

20 August 2023

20 August 2023

20 August 2023


Phase 3 (South)

JS9 - Enterprise (Contract J111)
In a nutshell: Foundation work is ongoing for the station structure while casting work is taking place for the viaduct piers near the Boon Lay station.

6 August 2023

27 August 2023

27 August 2023

31 August 2023


JS10 - Tukang (Contract J111)
In a nutshell: Site preparation works are ongoing.

31 August 2023

31 August 2023

31 August 2023


JS11 - Jurong Hill (Contract J111)
In a nutshell: Old pedestrian overhead bridge has been demolished and roadway is being prepared for diversion to make room for the work site in the road median.

31 August 2023

31 August 2023

31 August 2023


JS12 - Jurong Pier (Contract J112)
In a nutshell: Some basic structures can be seen at the base of the station. The additional exit connected via underpass has not begun work yet.

31 August 2023

31 August 2023

31 August 2023

31 August 2023

A similar but consolidated (a.k.a. less detailed) post will be available on Instagram & Facebook on 2 September 2023.

No comments:

Post a Comment