We've been on a journey re-looking back at the progress made through the year at the various Jurong Region Line (JRL) contracts. Thus far, we've gone through the phase 1 contracts, which you can view here:
Having completed the rotation of phase 1 contracts, we now venture into phase 2 territory. These stations will open a year later than their phase 1 counterparts and will serve a separate service on their own, unofficially called the eastern route, which consists of 7 stations. The first contract along this phase is Contract J108, which was awarded to a joint venture between McConnell Dowell & John Holland.
Milestones attained by this contract thus far have included the completion of casting all precast segmental boxes for viaducts, the commencement of roof frame installation works at two (2) stations and the commencement of linkbridges connecting to station exits at one (1) station. Of the phase 2 contracts, this one is slightly ahead of the others. More details after the jump.