24 September 2023 - Aerial view of the southern half of the station. |
Contract J106 has been bustling with work making significant progress over the past quarter. The station building is now becoming visible with the southern and northern halves using various pier support methods to keep the station elevated above Jurong West Street 64. Viaduct segment launching has also made significant progress with most spans installed. The only exception would be the spans that are supported by the movement & expansion joint piers. The installation of viaduct spans on these piers will require the use of trestles - a sort of frame that can hold the viaduct segments in place that is supported on the ground - and thus these spans are being left for the last parts of viaduct construction.