Monday, February 8, 2021

J102 - And its gone!

 

24 January 2021 - View of Choa Chu Kang interchange complex with block 303 demolished

Work on contract J102 has proceeded swiftly with demolition of Block 303 Choa Chu Kang central commencing in December 2020. A month later and the entire block has been brought down to make way for the new Jurong Region Line (JRL) being added to the station complex. As part of the JRL project, two additional platforms will be constructed at the station, allowing access from the North South Line (NSL) to the JRL.

Monday, February 1, 2021

J106 - Revised work time lines

 

12 January 2021 - Aerial view of the contract J106 site for Boon Lay station.

A recent visit to the contract J106 worksite earlier in January showed a new circular being issued by contractor China Communications Construction Company. In the circular, several dates for key work items have been pushed back.