Overview of JRL stations JS1 - JS8 as of August 2025. |
With August now done & dusted, we are really in the tail end of Q3 of 2025. That means its a mere 2 years to go till the first section of the Jurong Region Line (JRL) is set to open - we're not quite sure which part of 2027 this would be, but that is the target year. The major milestone achieved through August 2025 has been the completion of viaduct span construction works for another contract. With this, 5 out of 12 contracts have completed such works. More details can be found after the jump.