Monday, July 31, 2023

J108 - Tengah Plantation update Q2 2023

 

14 May 2023 - A view of the concourse slab that has been cast.
Source: LinkedIn

Having cleared our updates on the quicker-moving phase 1 of the Jurong Region Line (JRL), we're now starting our updates on the 7 stations that will form phase 2 of the line. The first of these is the hardest to reach - Tengah Plantation - which is sited in the middle of Plantation Crescent in Tengah new town. There is good news though, as the area is set to open up from around August with the home owners receiving their keys shortly. This means that the area will gradually become accessible in addition to having several vantage points from which the construction can be observed. We'll definitely be making use of these to bring you some updates.

Tuesday, July 25, 2023

J108 - Second launch gantry

 

24 July 2023 - The second launch gantry for contract J108 raised into position south of Tengah
Park station to begin work.
Source: LinkedIn

Yesterday, the second launch gantry for contract J108 was raised into position south of Tengah Park station. The gantry will begin work assembling the viaduct spans for the cripple siding located here. The lifting process utilised 2 mobile crane units that lifted the gantry in a process known as a tandem lift. Once elevated to the desired height, the cranes swung the gantry over to the final position atop the supports and the gantry was locked in place.

J105 - Bahar Junction update Q2 2023

 

29 June 2023

Rounding up our update for Phase 1 of the Jurong Region Line (JRL) at Q2 is Bahar Junction station, also under contract J105. Similar with Jurong West station, we had done an update in the early part of the quarter hence this update covers the remaining parts of the quarter of May & June 2023.

Thursday, July 20, 2023

J105 - Jurong West update Q2 2023

 

15 June 2023 - Concrete pumping in progress for the casting of the station concourse slab.

To finish off our Q2 2023 updates on the Jurong Region Line (JRL) phase 1, we visit contract J105 for the construction of Jurong West station. We had earlier done an update between Q1 & Q2, hence this update will cover the updates of the remaining months for Q2 2023.

Tuesday, July 18, 2023

J102 - Choa Chu Kang update Q2 2023

 

2 June 2023 - An aerial view of Choa Chu Kang Jurong Region Line (JRL) station work site.

23 March 2023 - A view of the station work site at the end of Q1 2023.

The past quarter has seen the station site at Choa Chu Kang take shape as rebar is installed and concrete poured. More of the station cable troughs and base slab can be seen being built. Installed rebar gives us an idea of where the facilities such as vertical transport and viaduct columns will go. Most of the work has progressed out of foundation works and will transit to the building of the station structure.

Thursday, July 13, 2023

J107 - Tawas update Q2 2023

 

29 June 2023 - A view of the under construction Tawas station.

15 June 2023 - An aerial view of Tawas station.

Further north at contract J107, is the second station under contractor CES_SDC's purview - Tawas. Located next to Cleantech Park, the station will serve the Jurong Innovation District area as well as the southeastern part of Nanyang Technological University. We take a look at how the site has progressed over the past quarter.

Tuesday, July 11, 2023

J107 - Gek Poh update Q2 2023

 

29 June 2023 - A view of construction along Jurong West Street 75 looking northwards, towards
Jurong West Street 82 & Tawas station.

Our next update brings us to contract J107 - specifically to Gek Poh. Things here are, like most other contracts for the Jurong Region Line (JRL), moving pretty quickly. Over the course of the last quarter, viaduct segment launching has commenced as has construction of part of the station concourse slab structure. Portal piers to the south are beginning to take shape as well and there's much to report from this neighbourhood. Full report after the jump.

Tuesday, July 4, 2023

J106 - Boon Lay update Q2 2023

 

29 June 2023 - A view of the station work site seen from block 661B.

Okay, this one is going to be a big update as there has been a lot of progress since our last update. For a more condensed update, do check out our Instagram or Facebook posts. Work has progressed fairly quickly within the last quarter over at contract J106 for the construction of Boon Lay Jurong Region Line (JRL) station and associated viaducts along Jurong West Street 64. Most of the viaduct piers have since been cast with approximately 4 to 5 left, whose columns have yet to be cast. The remaining viaduct piers are at various stages of completion, with some viaduct spans completed. The station area has progressed a little slower given its complexity but the first few pier supports there are beginning to take shape as well.