Showing posts with label JS08 - Boon Lay. Show all posts
Showing posts with label JS08 - Boon Lay. Show all posts

Saturday, April 26, 2025

J106 - An update in Q1 2025

An aerial view of the Boon Lay Jurong Region Line station in early & end Q1.

A lot has been happening at Boon Lay station on the East-West Line (EWL) as it prepares to be upgraded into an interchange with the upcoming Jurong Region Line (JRL). In addition to the new station being built, the existing station is undergoing several changes to cope with the increased passenger loads and commuter traffic. These works are being carried out under contract J106 which oversees the construction of the new station as well as the addition & alteration works to the existing EWL station. Milestones hit by the contract this past quarter include the completion of the roof frame installation, commencement of the construction of a replacement staircase within the existing station and the beginning of reinstatement works along Jurong West Street 64. We'll explore all these in greater detail after the jump.

Tuesday, December 10, 2024

J106 / Boon Lay - A 2024 progress report

 

To wrap the year, we've started a series called the 2024 progress report. This series aims to recap all the accomplishments and changes made through the work at the various sites over the year. Here are the other parts for the Jurong Region Line (JRL) thus far:

This contract has seen a lot of progress through 2024. Some of the highlights would include the completion of viaduct segment launching, the commencement of viaduct span preparation for handover to track laying contractor and the commencement of exit construction. Contractor China Communications Construction Co (CCCC) has been working steadily and safely in spite of all the challenges faced along the contract's length. We recap all of these after the jump.

Wednesday, August 7, 2024

J106 - Boon Lay update Q2 2024

16 June 2024 - An aerial view of the new JRL station building and viaducts of contract J106.

Contract J106 for the construction of Boon Lay station and viaducts for the Jurong Region Line (JRL) has seen steady progress at its site through Q2 of the year. Through the quarter, the station building has continued to take shape with the structure rising from the concourse level on the third floor to the platform level on the fourth floor. Eventually, both halves of the station to the north and south of the existing East-West Line (EWL) viaduct will meet above the operational line.

Thursday, April 18, 2024

J106 - Boon Lay update Q1 2024

 

21 March 2024 - An aerial view of Boon Lay station as at end-Q1 2024.

The Boon Lay Jurong Region Line (JRL) will be one of the tallest when completed in 2027, with the station spanning across 4 levels. Over the past quarter, works have progressed on the station's superstructure, quickly gaining height on both the northern and southern sections. The two sections will eventually meet in the middle, right atop of the existing East-West Line (EWL) viaducts. Elsewhere along contract J106's construction sites, work has been underway to complete the gaps in the viaduct spans where the movement expansion joints are located. More details can be found after the jump.

Thursday, November 30, 2023

J106 - Boon Lay update Q3 2023

 

24 September 2023 - Aerial view of the southern half of the station.

Contract J106 has been bustling with work making significant progress over the past quarter. The station building is now becoming visible with the southern and northern halves using various pier support methods to keep the station elevated above Jurong West Street 64. Viaduct segment launching has also made significant progress with most spans installed. The only exception would be the spans that are supported by the movement & expansion joint piers. The installation of viaduct spans on these piers will require the use of trestles - a sort of frame that can hold the viaduct segments in place that is supported on the ground - and thus these spans are being left for the last parts of viaduct construction.

Tuesday, July 4, 2023

J106 - Boon Lay update Q2 2023

 

29 June 2023 - A view of the station work site seen from block 661B.

Okay, this one is going to be a big update as there has been a lot of progress since our last update. For a more condensed update, do check out our Instagram or Facebook posts. Work has progressed fairly quickly within the last quarter over at contract J106 for the construction of Boon Lay Jurong Region Line (JRL) station and associated viaducts along Jurong West Street 64. Most of the viaduct piers have since been cast with approximately 4 to 5 left, whose columns have yet to be cast. The remaining viaduct piers are at various stages of completion, with some viaduct spans completed. The station area has progressed a little slower given its complexity but the first few pier supports there are beginning to take shape as well.

Saturday, May 13, 2023

J106 - Boon Lay update Q1 2023

19 March 2023

We now check in on contract J106 for the construction of Boon Lay station and associated viaducts. Apart from contracts J102 and J108, this contract was another to begin viaduct construction work early. Instead of using a launching gantry to lift segmental box girders into position, this contract instead uses the lifting frame method. Let's check in on the progress made in Q1 of 2023.

Saturday, December 24, 2022

J106 - Boon Lay year-end update

 

16 December 2022 - An aerial view of the station site with the protected train viaducts visible.

16 December 2022 - Caisson construction work taking place.

Boon Lay station site is one that has undergone tremendous transformation over the course of the year. Traffic diversions have been implemented to allow for construction to take place over the location of the former roadway as there would not have been sufficient space to keep the roadway operational while works are carried out. The station itself will be an engineering feat, with the platforms elevated 2 stories above the existing East-West Line (EWL) tracks. To ensure that train services on the EWL are not disrupted, temporary protective enclosures have been progressively installed on the viaduct of the operational train line.

Tuesday, November 22, 2022

J106 - Update on site progress

 

17 November 2022 - A view northwards along Jurong West Street 64,
as seen from the Frontier Community Club.

17 November 2022 - A rebar cage on site for pier construction. The stub for a pier can also be
seen towards the left of the image.

We are back at contract J106 to view the progress in the middle of the month. Despite the previous visit being fairly recent, there's a fair bit of visible progress at the site. More piers can be seen, apart from the 2 completed ones at the northern end of the contract. From the north, the third pier is half-cast whilst the sixth was having formwork being done to facilitate the casting works. The stubs of piers four and five from the northern contract boundary are visible as well.

Saturday, November 5, 2022

J106 - 1, 2, completed piers, 3, 4, upcoming main shafts

30 October 2022 - The first 2 completed viaduct piers for the contract.

30 October 2022 - A view of the 2 piers from street level, looking northwards.

We seem to be having a thing going with piers being fully cast and ready as of late. Here's some continuing coverage of viaduct piers from contract J105 in our previous post to contract J106. The completed piers within J106's domain are located at the northern end of the contract site. Currently, 2 fully cast piers are visible standing tall above the road.

Tuesday, October 18, 2022

J106 - Roads back & now for the bicycle park

 

9 October 2022 - A view of both bounds of Jurong
West Street 64 diverted atop the canal.

In our previous visit to Boon Lay, we covered the preparations for the road diversion. Last weekend, the road was again shifted, but away from the temporary split configuration. Both bounds are now back together again, side by side. This shift will allow the former location of the roadway to be transformed into a work site to enable the construction of the Jurong Region Line (JRL) station above.

Tuesday, October 4, 2022

J106 - Reuniting the road

 

Circular by contractor on changes to pedestrian footpaths following the upcoming road diversion.
Source: China Communications Construction Co. via Telegram

Circular by contractor on the upcoming road diversions this weekend.
Source: China Communications Construction Co. via Telegram

Following the successful road diversion phase 1 at the contract J106 site, contractor China Communications Construction Co. will be moving the southbound lanes of Jurong West Street 64 atop the canal. Part of the canal has been decked over to allow the roadway to be shifted atop. This allows the former area occupied by the roads to be freed up for station foundation works. Once the roadway has been diverted, residents in the area can expect the asphalt and any supporting utilities (e.g. drains, lighting, cabling) to be moved out of the way. The cleared site can then be used for bored piling works before the frame of the station can come up.

Saturday, September 17, 2022

J106 - The road has parted

10 September 2022 - An aerial view showing the existing EWL Boon Lay
station, the JRL station site & the newly diverted northbound road.

Following works that commenced a day prior on 9 September, the northbound carriageway of Jurong West Street 64 was diverted on top of the canal running parallel to the roadway. The road diversion will free up space for the construction of the Jurong Region Line (JRL) station which will be located on top of the street, straddling the existing East-West Line (EWL) station and tracks. In this post, we take a look at the changes implemented on 10 September at the site.

Friday, September 9, 2022

J106 - Road diversion at Boon Lay

Notice by the contractor regarding road diversion works. Also indicated
on the notice is the location of the JRL Project Information Centre (PIC)
which we had referenced before.

According to the contractor for J106, works to facilitate a road diversion will begin today and complete by tomorrow. This is to allow the space currently taken by Jurong West Street 64 to used for the construction of the Jurong Region Line (JRL) station at Boon Lay. Here's a look back at all the work that has taken place thus far.

Monday, June 6, 2022

Video flythroughs

 

A render of Boon Lay station on the Jurong Region Line.
Source: Facebook

As it has been approximately 4 years since the Jurong Region Line (JRL)'s final alignment was announced to the public in May 2018, several images of the stations have been made available showing the minor details that distinguish each station from another. Whilst using a basic design skeleton that features a vaulted roof supported along the sides by several columns, each station manages to retain some level of individuality. Several videos have since allowed us to catch a glimpse of the designs of the upcoming stations.

Friday, September 24, 2021

JRL1 Construction update - Q3 2021

8 September 2021 - A view of the Choa Chu Kang interchange site as seen from an MRT train.

It has been a few months since our last update and unfortunately, there has not been too much progress on the line's construction. Majority of the works are still focused on the preliminary stages of utility diversion and site preparation. At some sites, there has not been much visible progress while others show a bit more visible work. In this update we'll do our best to give an overall summary of the progress.

Monday, February 1, 2021

J106 - Revised work time lines

 

12 January 2021 - Aerial view of the contract J106 site for Boon Lay station.

A recent visit to the contract J106 worksite earlier in January showed a new circular being issued by contractor China Communications Construction Company. In the circular, several dates for key work items have been pushed back.

Monday, November 9, 2020

J106 - Upcoming work at Boon Lay

 

08 November 2020 - An aerial view of the Boon Lay East West Line station with the LTA Project office in the background

The site around Boon Lay station has undergone some changes since the update of the site of the future Jurong Region Line (JRL) interchange station. Since our last visit to Contract J106's site, more site offices have sprung up in the vicinity of the Land Transport Authority (LTA) Project Office and the main contractor has also issued a new circular detailing upcoming works.

Wednesday, July 8, 2020

Contract update - J106 Boon Lay

Contact J106 for the construction of Boon Lay station on the Jurong Region Line (JRL) was awarded in February 2020 to China Communications Construction Company. Since the award date, there has yet to be much movement at the site of the future station which will sit perpendicularly a level above the existing East West Line train tracks.

02 July 2020 - Aerial view of Boon Lay station site from the south

Tuesday, February 18, 2020

Contract awards - J151, J106, J107 & J110

Render of the contract J151 trains by Hyundai Rotem.
Source: LTA
February has been a milestone month in the progress of the Jurong Region Line (JRL) with the award of 4 major contracts for the line. These include contracts for supply of trains for the line as well as the construction of 2 stations and 2 interchanges.