Thursday, September 30, 2021

JRL3 Construction Update - Q3 2021

 

25 September 2021 - Slope stabilization works at Jurong Hill station site.

Phase 3 of the Jurong Region Line will be the last stage of the line to be commissioned.  This phase comprises of approximately 4 contracts - J111, J112, J113 & J115A. Of these, three have since been awarded, with 1 contract - J115A - being re-tendered. As this section of the line will be commissioned around 2028 to 2029, the works at the sites are not at an advanced stage yet with mostly utility works in progress. This is likely due to the contracts being recently awarded as well.

Friday, September 24, 2021

JRL1 Construction update - Q3 2021

8 September 2021 - A view of the Choa Chu Kang interchange site as seen from an MRT train.

It has been a few months since our last update and unfortunately, there has not been too much progress on the line's construction. Majority of the works are still focused on the preliminary stages of utility diversion and site preparation. At some sites, there has not been much visible progress while others show a bit more visible work. In this update we'll do our best to give an overall summary of the progress.