Sunday, October 29, 2023

J102 - Choa Chu Kang update Q3 2023

 

24 September 2023 - An overview of the station site at the end of Q3 2023.

Work over at Choa Chu Kang station has been barreling along with major progress made over the past quarter. Station columns have gone up and the viaduct piers parallel to the North-South Line (NSL) and Bukit Panjang LRT tracks have sprung up with crosshead construction beginning as well. Be warned, this post is going to be a long one and photo-heavy.

Saturday, October 21, 2023

J108 - Bukit Batok West update Q2 & Q3 2023

 

16 April 2023 - An aerial view of the station site in early Q2 2023.

Bukit Batok West has been like the middle child in a family of 3 children - there but sometimes a little overlooked. Contract J108 is for the construction of viaducts and stations JE1, JE2 and JE3 for the Jurong Region Line (JRL). With so much action taking place at Tengah Plantation (JE1) and Tengah Park (JE2), with both stations having visible structures up to the concourse level, it doesn't take a rocket scientist to figure out why there hasn't been a lot of coverage of Bukit Batok West. Nonetheless, the sleepy station is finally finding its footing and coming out of its long slumber to show some signs of progress. Do read on to find out more.

Sunday, October 15, 2023

J115A - Peng Kang Hill update Q3 2023

 

16 September 2023 - A view of the work site and the valley through which the line will travel
before arriving at the terminus within NTU.

Contract J115A was the last of the civil contracts for the Jurong Region Line (JRL) to be awarded. As such, construction within the contract is not at such an advanced stage despite being awarded to the same contractor responsible for the neighbouring contract J113 for Nanyang Gateway & Nanyang Crescent station. This is likely due to cost reduction measures which resulted in the contract having to be re-tendered. The original contract J115 had also included works for the remote stabling facility to be constructed next to the Peng Kang Hill station. Under the revised contract J115A only provision stubs will be catered for to connect to such a facility in future.

Sunday, October 8, 2023

J113 - More piers in NTU | Nanyang Gateway update Q3 2023

 

1 September 2023 - A view of the station site for Nanyang Crescent along Nanyang Avenue,
looking eastwards.

Over the past 9 months since we last updated on the stations at Nanyang Technological University (NTU), the various construction sites here have made some significant progress. Contract J113 for the construction of Nanyang Gateway and Nanyang Crescent  Jurong Region Line (JRL) stations has seen quick progress with several piers slowly climbing upwards as work progresses within the university. In our previous post, we covered the semi-completed piers near Nanyang Crescent station, thus this post will focus on the sites near to Nanyang Gateway station.

Sunday, October 1, 2023

J113 - First phase 3 piers in NTU | Nanyang Crescent update Q3 2023

 

16 September 2023 - A view of one of the approximately 8 piers currently under construction for
phase 3 of the Jurong Region Line.

During our time away from Nanyang Technological University (NTU), work has progressed to the extent that there are now several piers under construction at various stages within contract J113. These represent the first piers of phase 3 of the Jurong Region Line (JRL), which consists of 4 contracts awarded to 3 different sets of contractors. The contractor for all contracts within NTU happen to be the same. As of the time of visit, approximately 8 piers were in progress. The 4 closest to Nanyang Crescent station were at the most advanced stage of construction of the 8, owing to the topography of the area where the pier columns will not be excessively high.