Sunday, October 8, 2023

J113 - More piers in NTU | Nanyang Gateway update Q3 2023

 

1 September 2023 - A view of the station site for Nanyang Crescent along Nanyang Avenue,
looking eastwards.

Over the past 9 months since we last updated on the stations at Nanyang Technological University (NTU), the various construction sites here have made some significant progress. Contract J113 for the construction of Nanyang Gateway and Nanyang Crescent  Jurong Region Line (JRL) stations has seen quick progress with several piers slowly climbing upwards as work progresses within the university. In our previous post, we covered the semi-completed piers near Nanyang Crescent station, thus this post will focus on the sites near to Nanyang Gateway station.

Station site
At the beginning of the year, the station site had implemented a road diversion that pushed Nanyang Avenue further north, towards Halls 10 & 11. This followed the completion of works to cover up the large drain that was present there and allowed for station foundation works to commence at the site of the former roadway.

In September, bored piling works were well underway at the site that will create the foundation for the station which will be directly above the roadway.

19 February 2023 - A westward view along Nanyang Avenue.

19 February 2023

12 March 2023 - A westward view along Nanyang Avenue.

12 March 2023

12 March 2023

1 September 2023 - An eastward view along Nanyang Avenue.

1 September 2023 - Hoarding visible for the JRL work sites.

1 September 2023 - Approaching the site of the station, located in the distance.

1 September 2023

16 September 2023 - Bored pile works for the viaduct foundations next to Nanyang Heights.

16 September 2023 - The station site looms in the distance.

16 September 2023 - A view of the station site, sandwiched between Hall 10/11 & Nanyang Grove.

16 September 2023 - A close up view of bored piling works underway for the station foundation.

16 September 2023 - The former bus stop shelter is still intact on site.

16 September 2023 - A westward view of the diverted Nanyang Avenue.

16 September 2023

16 September 2023

16 September 2023

Viaduct site east
The viaduct site to the east of the station will see the line swinging south to connect with the viaduct at neighbouring contract J107, north of Tawas station. In the earlier part of the year, the site was rather nondescript with not much activity taking place.

However by September, one of the first piers here could be seen being constructed with the rebar skeleton being established first. Later on, the rebar was encased in formwork and casting would take place. As of September, only 1 pier has been noted to be under construction here.

19 February 2023 - A view of the contract boundary site with contract J107 to the south.

1 September 2023 - A view of the same area several months later.

1 September 2023

1 September 2023 - The rebar skeleton of the viaduct pier visible.

16 September 2023 - The viaduct pier encased in formwork for casting.

Viaduct site west
To the west of the Nanyang Gateway station, work was also taking place on various viaduct piers that will connect the station with Nanyang Crescent station. The hive of activity is centred around the valley just in front of Hall 8. Earlier in the year works were in a rather initial stage with the site being prepared for construction.

By September, the beginnings of viaduct columns could be seen. In the middle of the month, the bottom halves of the viaduct columns had been completely cast, with further work on the upper halves still remaining. Due to the undulating topography of the area, the viaduct piers at this site will need to rise higher to meet the elevation required for approaching Nanyang Crescent station. As of September, approximately 4 piers were noted to be under construction here. With the pier at the eastern viaduct site and the others near to Nanyang Crescent station, NTU now has at least 9 piers at varying stages of construction that are fully visible.

12 March 2023 - A view of the valley in front of Hall 8 where the
viaduct piers will be built.

12 March 2023

1 September 2023 - Part of a pier being cast can be seen over the top of the hoarding.

16 September 2023

16 September 2023 - A close up view of the viaduct pier column being constructed.

16 September 2023 - A view of the several viaduct piers under construction.

16 September 2023

16 September 2023 - A view of the partially cast bottom half of the viaduct pier.

16 September 2023 - A viaduct pier encased in formwork.

16 September 2023

16 September 2023 - A view of the valley in front of Hall 8 where the line curves up to reach
Nanyang Crescent.

16 September 2023

Casting yard site
The casting yard for contract J113 is located in a shared space with the yard for contract J111 along Tractor Road. Since being set up, work has progressed to churn out precast segmental box girders for use in NTU to construct the JRL viaducts.

16 April2 2023 - Gantry cranes on site bearing the contractor Hwa Seng Builder (HSB)'s logo.

16 April2 2023 - The casting yard is co-located with that for contract J111.

2 June 2023 - A view of formwork for the precast viaduct segments on site at the casting yard.

2 June 2023 - A view into the casting yard for contract J113.

31 August 2023 - A view of the contract J113 casting yard in the midground. Several precast
viaduct segmental box girders can already be seen.

31 August 2023

31 August 2023

31 August 2023

28 September 2023 - A view of the precast viaduct segmental box girders in the background for
contract J113.

With several viaduct piers already being cast, it will be a matter of time before viaduct construction begins within the university. We look forward to further milestones being achieved for the third phase of the line and will be sure to bring you updates on these in due time.

This post will also be available on Instagram & Facebook on 9 October 2023.

No comments:

Post a Comment