Thursday, October 7, 2021

J108 Construction Update - Q3 2021

25 September 2021 - A view of the route as the line swings in to Tengah estate as seen from Bukit Batok Road.

Phase 2 of the Jurong Region Line (JRL) is the final phase we cover in our update for Quarter 3 of 2021. This phase consists of 4 contracts - J108, J109, J110 and J120 for the construction of various parts of viaducts and stations. Contract J108 was won by John Holland-McConnell Dowell and will connect phase 2 to the rest of the line at phase 1's Tengah interchange station. The contract will involve the construction of 3 stations at Tengah Plantation, Tengah Park & Bukit Batok West.

As this post is rather photo-heavy, we have decided to break the post up according to contract for easier readability. Do look out for our subsequent posts on other sections of the line.

Thursday, September 30, 2021

JRL3 Construction Update - Q3 2021

 

25 September 2021 - Slope stabilization works at Jurong Hill station site.

Phase 3 of the Jurong Region Line will be the last stage of the line to be commissioned.  This phase comprises of approximately 4 contracts - J111, J112, J113 & J115A. Of these, three have since been awarded, with 1 contract - J115A - being re-tendered. As this section of the line will be commissioned around 2028 to 2029, the works at the sites are not at an advanced stage yet with mostly utility works in progress. This is likely due to the contracts being recently awarded as well.

Friday, September 24, 2021

JRL1 Construction update - Q3 2021

8 September 2021 - A view of the Choa Chu Kang interchange site as seen from an MRT train.

It has been a few months since our last update and unfortunately, there has not been too much progress on the line's construction. Majority of the works are still focused on the preliminary stages of utility diversion and site preparation. At some sites, there has not been much visible progress while others show a bit more visible work. In this update we'll do our best to give an overall summary of the progress.

Monday, February 8, 2021

J102 - And its gone!

 

24 January 2021 - View of Choa Chu Kang interchange complex with block 303 demolished

Work on contract J102 has proceeded swiftly with demolition of Block 303 Choa Chu Kang central commencing in December 2020. A month later and the entire block has been brought down to make way for the new Jurong Region Line (JRL) being added to the station complex. As part of the JRL project, two additional platforms will be constructed at the station, allowing access from the North South Line (NSL) to the JRL.

Monday, February 1, 2021

J106 - Revised work time lines

 

12 January 2021 - Aerial view of the contract J106 site for Boon Lay station.

A recent visit to the contract J106 worksite earlier in January showed a new circular being issued by contractor China Communications Construction Company. In the circular, several dates for key work items have been pushed back.

Monday, January 25, 2021

J107 - LTA updates

Artist's impression of Gek Poh station
Source: Foo Mee Har

In the time since our last update, we've been grateful to have been supplied with information by Ms. Audrey Teo who lives near to the upcoming Gek Poh station. In a circular to residents, the Land Transport Authority explains the upcoming works under contract J107.

Monday, December 7, 2020

J109 - Soil investigation & Utility tracing

 

18 April 2019

Contract J109 entails the construction of Toh Guan, Jurong Town Hall and Pandan Reservoir stations for the Jurong Region Line (JRL). A strange contract as it is broken into two sections - the northern section which involves Toh Guan station and the southern section which involves the other 2 stations. In between are contracts J120 and J110 for the construction of viaducts through the Jurong Hub integrated development & construction of Jurong East interchange station respectively.