Tuesday, September 24, 2024

J110 & J120 - Jurong East update Q2 & Q3 2024

Contracts J110 (top) and J120 (bottom) as of end-Q3.

To speed things up and keep our updates a little more current, we'll be combining the updates for both Q2 and Q3 for the remaining contracts (J110, J111, J112, J113, J115A & J120) of the Jurong Region Line (JRL). Hopefully, this gives our reads a more timely perspective of the works progression.

JE5 - Jurong East (Contract J110)
Over the past two quarters, the station has progressed steadily. At the beginning of Q2, the concourse slab had not yet been cast, however at end-Q3, works were making progress on the casting of the lower platform level.

1 May 2024 - A view westwards of the station structure with scaffolding in place for progress of
the concourse level slab.

2 June 2024 - Rebar installation works underway for the concourse level slab.

2 June 2024 - An aerial view of the existing station, with part of the JRL station visible.

16 June 2024 - Progress of works for the concourse level slab. At the western end, columns are
visible at the concourse level.

18 July 2024 - A view of concourse level columns progressing upwards to the lower platform
level.

18 August 2024 - A view westwards in mid-Q3, with the concourse level cast. Columns at the
concourse level were steadily making progress with work at the western end of the station moving
on at the lower platform level.

8 September 2024 - A view of the station's progress seen from the south in end-Q3.

Transfer hub & plaza
At the station's western end, the former main entrance is being transformed into a transfer hub & plaza area. The transfer hub will connect the new station extension with the existing station building, allowing transfers between the existing platforms and the new Pandan Reservoir-bound track at the upper platform level of the JRL station. The area below the transfer hub will be a plaza area that allows passengers to connect to the Jurong Hub development where the bus interchange will be located. Additionally connections at the second level will allow passengers at the station concourse to connect to Westgate and the Jurong Hub developments through an expanded J-walk network - the elevated pedestrian network around Jurong East station.

1 May 2024 - A view of works progressing at the transfer hub & plaza in mid-Q2.

1 May 2024 - Viaduct piers for the JRL under construction. There will be 2 piers here constructed
under contract J110.

1 May 2024 - Rebar of the second pier under contract J110.

1 May 2024 - A view of structural works for the plaza at ground level.

1 May 2024 - Another view of structural works for the plaza in mid-Q2.

1 May 2024 - Plaza works in the foreground and viaduct piers in the background.

2 June 2024 - A view of the structural works at the transfer plaza & hub in end-Q2.

2 June 2024

2 June 2024 - Concrete pours have been completed for some of the plaza's base slab.

2 June 2024

2 June 2024 - A view of progress at the two viaduct piers being built at the western end by
contract J110.

2 June 2024 - A close up view of the western-most viaduct pier.

2 June 2024 - A view of the ongoing works. The roof structure of the original station can still
be seen for now. The transfer hub will eventually block this view.

2 June 2024 - Looking beyond the transfer hub & plaza to the contract J120 site.

16 June 2024 - A tower crane was being installed at the contract J120 site in end-Q2.

16 June 2024 - Another view of the viaduct piers at the western end of contract J110.

16 June 2024

16 June 2024 - A close up view of the western-most viaduct pier under contract J110.

16 June 2024

18 July 2024 - A view of the plaza's site in early-Q3. Rebar for some of the columns has since
been installed to support the transfer hub above.

8 September 2024 - A view of the plaza construction site in end-Q3. The rebar for the column
previously seen had since been cast in concrete.

Station building 
The eastern end of the Jurong East station is the slowest to progress, with works at the western end taking the slight lead. Over the past 2 quarters, the works at this end have progressed to the lower platform level. A viaduct pier just before the station is also being constructed here, consisting of 2 square columns supporting the split level tracks at the station.

Over at the western end, works through the quarters had seen the columns grow from the concourse level up to the lower platform level. Rebar installation was underway towards the end of Q3 ahead of casting works proceeding.

12 May 2024 - A view of the eastern-most viaduct pier base in mid-Q2.

2 June 2024 - A view of the base of the viaduct pier in end-Q2.

18 August 2024 - A view of the viaduct pier with rebar for one of the columns since installed as
of mid-Q3.

15 September 2024 - A view of rebar for both columns installed at the eastern end as of end-Q3.

12 May 2024 - A view of the station's eastern end in mid-Q2. Scaffolding assembly for the
installation of the concourse level formwork was taking place.

12 May 2024 - Moving further west, the scaffolding gets progressively more complete for the
next phase of works.

12 May 2024 - Views of the concourse level, already cast, begin to make an appearance further
west.

12 May 2024 - The western-most end of the station, which is flushed with the existing
North-South-East-West Line station building.

12 May 2024 - Viaduct piers for the western end in view, as of mid-Q2.

23 May 2024 - Progress of formwork installation at the station's eastern end.

2 June 2024 - An aerial view of the station's eastern end in end-Q2.

2 June 2024 - Rebar for the concourse level columns making an appearance.

2 June 2024 - A view of the station's eastern end, looking westwards. The rebar for the viaduct
pier at the eastern end can be seen awaiting installation.

2 June 2024 - With formwork in place for most of the eastern end, rebar installation work could
proceed.

2 June 2024 - A view of the interface zone where the section with concrete casting meets the section
with rebar installation underway.

2 June 2024 - Concourse level columns beginning to make an appearance close to the interface
zone.

2 June 2024 - Columns near the western end already beginning the casting process.

2 June 2024 - A view of one of the viaduct pier columns.

2 June 2024 - And the second viaduct pier column.

16 June 2024 - Work at the station's eastern end, concourse level.

16 June 2024

16 June 2024 - The station's eastern end, looking westwards. Rebar columns for the viaduct pier
can still be seen here.

16 June 2024

16 June 2024 - Rebar for the concourse level columns at the station's western end have been
installed. Formwork has also been set up at the base of the columns.

16 June 2024

16 June 2024 - Progress of the western viaduct pier columns.

23 June 2024 - Rebar installation for the concourse level nearly completed at the eastern end.

23 June 2024

23 June 2024 - Concourse level columns advancing towards the interface zone.

23 June 2024 - With the columns cast, other structures are following suit.

23 June 2024

23 June 2024

14 July 2024 - Concourse level slab progress at the station's eastern end. Columns had been going
up at this end as well.

14 July 2024

14 July 2024 - The openings seen may be used for installation of escalators, lifts or utilities.

14 July 2024 - Scaffolding installation underway for the lower platform level works at the
station's western end.

18 August 2024 - Concourse level columns at the station's eastern end.

18 August 2024 - Most of the structures at concourse level, including plant and utility rooms, had
been cast.

18 August 2024

18 August 2024 - Formwork installation underway for the lower platform level in the station's
centre section.

18 August 2024 - Rebar installation underway near the western end.

8 September 2024 - A view of the protective screen installed along the westbound track of the
existing station.

8 September 2024 - Further eastwards, the line of rebar columns could be seen making an
appearance.

8 September 2024 - A view of the progress of rebar installation works.

8 September 2024 - Rebar installation work progress at the station's western end.

Jurong East Integrated Transport Hub & viaducts (Contract J120)
The contract for the construction of the Jurong Hub development includes the construction of viaducts between contracts J109 and J110, running through the Jurong Hub integrated transport hub. Part of the development will be supported by the viaduct piers that will also carry the viaduct spans for the JRL. Through the past 2 quarters, span construction and in-situ casting has been continuing. The number of spans either completely cast or beginning construction works have increased from 3 per bound to 5 per bound. The spans towards the western end are the most advanced among the 5 spans being worked on.

1 May 2024 - A view of the first pair of completed viaduct spans in mid-Q2.

2 June 2024

18 July 2024 - A view of the first 3 pairs of viaduct spans at the western end of the contract.

17 August 2024 - The interface section between pairs 1 and 2 of the viaduct spans.

8 September 2024 - The third through fifth pairs of spans under construction in end-Q3.

Some significant works that began in Q3 include the commencement of parapet wall installation works. These began on the first pair of spans constructed and will be progressively installed further east as more viaduct spans continue to be completed.

1 May 2024 - An aerial view looking eastwards at the project site.

1 May 2024 - A close up view of the first 2 pairs of viaduct spans.

2 June 2024 - An aerial view from the north of the first 2 pairs of viaduct spans.

2 June 2024 - Ongoing works to ready the site for the next spans for construction.

2 June 2024 - Viaduct piers near the Jurong Hub development can barely be seen.

7 July 2024 - The viaduct pier columns had begun appearing.

7 July 2024 - A view of the first 2 pairs of viaduct spans, seen from the west.

14 July 2024 - Work on the third span progressing towards the subsequent pier crosshead.

14 July 2024 - Scaffolding installation for the fourth pair of spans ongoing.

14 July 2024 - An aerial view of the site, looking eastwards.

14 July 2024 - A view of the progress of the viaduct pier columns.

14 July 2024 - An aerial close up view of the project site from the west.

14 July 2024

14 July 2024 - A close up view of the first 3 pairs of viaduct spans.

18 July 2024 - The first 3 pairs of viaduct spans under construction.

18 August 2024 - As the third pair of spans is being constructed, work for the fourth pair
commences.

18 August 2024 - A view of the contract's western end, seen from the north.

18 August 2024 - Casting of the first 2 pairs of spans was completed, with works focused on the
third and fourth pairs.

18 August 2024 - Scaffolding preparation for the fifth pair of viaduct spans can be seen.

18 August 2024 - A view of the viaduct span construction progress as a North-South Line train
approaches the work site.

18 August 2024 - An aerial view of the site with the Jurong East station visible in the background.

18 August 2024 - An aerial view of the project site in mid-Q3.

18 August 2024 - A close up view of the first few completed viaduct spans. Parapet wall installation
works had yet to begin.

18 August 2024 - The work site with one of the first generation MRT trains running on the
westbound track.

18 August 2024 - The progress of works seen from Teban Gardens.

2 June 2024 - A view westwards with the first 2 pairs of spans in progress.

2 June 2024 - Formwork was still in place for the second pair of spans.

10 August 2024 - A view of work commencing for the third pair of viaduct spans as an eastbound
seventh generation MRT train approaches Jurong East station.

10 August 2024 - A close up view of the work taking place for the third pair of viaduct spans.

10 August 2024

8 September 2024 - The eastern-most viaduct pier of the contract had been cast up to crosshead
level. This pier is likely to be a movement & expansion joint pier.

8 September 2024 - Another view of the eastern-most viaduct pier under the contract, seen from
a westbound train.

8 September 2024 - A view of the first pair of viaduct spans. Parapet walls can be seen at the edge
of the Pandan Reservoir-bound viaduct span.

8 September 2024

8 September 2024 - A view of formwork for the third and fourth pair of viaduct spans.

8 September 2024 - A view of parapet walls installed on the Tengah-bound viaduct span.

8 September 2024

15 September 2024 - An aerial view of the viaduct spans seen from the north.

15 September 2024 - Subsequent pairs of viaduct spans under construction.

15 September 2024 - A close up view of the formwork for the third and fourth pairs of viaduct
spans.

15 September 2024 - A view of viaduct spans with casting works in progress.

15 September 2024

Through the past 2 quarters, great progress has been made which can be seen in the changes at the two sites. As we head into the tail end of the year, we're merely 4 years away from this section of the line becoming a reality for commuters in the area. Till then, we'll do our best to keep you updated on the progress being made.

This post will also be available on Instagram & Facebook on 26 September 2024.

No comments:

Post a Comment