| A compilation of stations under contract J111 under construction in September 2023. |
![]() |
| A compilation of stations under contract J111 under construction in September 2023. |
![]() |
| 24 September 2023 - A view of works at the Jurong East interchange under contract J110 as of end-Q3 2023. |
![]() |
| 17 September 2023 - A view of parts of the contract J120 viaduct under construction as at end-Q3 2023. |
![]() |
| A compilation of progress at the 3 station sites as at September 2023. |
![]() |
| Stations under contract J108 as on 24 September 2023. |
A lot has happened last quarter over at contract J108 which is for the construction of 3 phase two stations at Tengah Plantation, Tengah Park & Bukit Batok West. Also part of the package are viaducts from Tengah Junction, where the line diverges from the western route, up to the interface with contract J109 along the Pan Island Expressway (PIE), south of Bukit Batok town. In order to speed up the updates ahead of the year-end recap that we're in the midst of preparing, we're updating the rest of the line by contract. Head on past the jump for loads of pictures about the progress made over Q3 2023.
![]() |
| 24 September 2023 - A view of Tawas station as seen from the north. |
As of the end of Q3 2023, work at the Tawas station was progressing to casting of the trackbed & platform level support columns. Using precast platform level crossheads, the side platform slabs of the station will be supported by central columns below the trackbed. Apart from Tengah station, Tawas is likely to be one of the Jurong Region Line (JRL) stations to be built the quickest. Join us as we take a look at the progress made over the past quarter.
![]() |
| 28 September 2023 - A view of Gek Poh station seen from street level at end-Q3 2023. |
Quarter 3 of the year has seen some milestones being achieved for the Gek Poh station and surrounding viaducts. These include the completion of casting of all the station pier's concourse level crosshead stubs, the installation of one prefabricated crosshead arm, completion of several viaduct spans and the commencement of construction of another portal pier's beam. Head on after the jump to find out more!
November has been a busy month for all Jurong Region Line (JRL) contractors. A fair number of viaduct spans have been completed in the past month and station construction has come some way along with several stations moving to work on the platform levels. Here's a look back at the November snapshot of work progress on the line.