Friday, June 28, 2024

JRL - A snapshot in June 2024

Overview of JRL stations JS1 - JS8 as of June 2024.
Top (L - R): JS1 - Choa Chu Kang, JS2 - Choa Chu Kang West, JS2A - Forest Hill
Middle (L - R): JS3 - Tengah, JS4 - Hong Kah, JS5 - Corporation
Bottom (L - R): JS6 - Jurong West, JS7 - Bahar Junction, JS8 - Boon Lay


Overview of JRL stations JW1 - JW2 & JE1 - JE7 as of June 2024.
Top (L - R): JW1 - Gek Poh, JW2 - Tawas, JE1 - Tengah Plantation
Middle (L - R): JE2 - Tengah Park, JE3 - Bukit Batok West, JE4 - Toh Guan
Bottom (L - R): JE5 - Jurong East, JE6 - Jurong Town Hall, JE7 - Pandan Reservoir


Overview of JRL stations JW3 - JW5 & JS9 - JS12 as of June 2024.
Top (L - R): JS9 – Enterprise, JS10 – Tukang, JS11 – Jurong HillJW3 - Nanyang Gateway
Middle (L - R): JS12 – Jurong Pier, JW3 – Nanyang Crescent, JW4 – Nanyang Gateway 
Bottom (L - R): JW5 – Peng Kang Hill, Contract J101 Tengah depot, Contract J120 Jurong East ITH

We are quickly approaching the mid-point of the year. The progress along the Jurong Region Line (JRL) is also beginning to pick up the pace further. This snapshot feature brings you a quick update on the progress made over the past month across the JRL.

Tuesday, June 11, 2024

J102 - A deep dive into Choa Chu Kang's modifications

Graphical representation of the existing Choa Chu Kang North-South Line station concourse and
transfer mezzanine level before the Jurong Region Line expansion.

Graphical representation of the Choa Chu Kang station concourse & transfer mezzanine levels
after modification works for the Jurong Region Line.

There has been a lot of work going on at Choa Chu Kang station ahead of the Jurong Region Line (JRL)'s arrival in 2027. All these works will serve to allow the station to increase its capacity for handling commuter traffic. What are the works taking place and how will these help to increase the station's capacity you may ask? We're here to break it down so that you'll be able to better understand the ongoing works.

Modification works at Choa Chu Kang station entail the following:

  • Demolition of former Exit D & using this area for an expanded concourse fare paid area linking the North-South Line (NSL) & JRL
  • Construction of a second lift to serve the existing NSL platform
  • Addition of new mezzanine level on the northern side of the station to facilitate transfers between NSL & JRL
  • Demolition, replacement & reconfiguration of existing escalators & staircases connecting NSL concourse & platform levels
  • Expansion of existing mezzanine level on southern side of the station to facilitate transfers between NSL, JRL & BPLRT
  • Reconfiguration of existing fare gate layout from one fare line to 3 fare lines
  • Reconfiguration of circulation spaces within fare paid & fare unpaid areas of the NSL station concourse
  • Reconfiguration of retail outlets within NSL station
  • Relocation of passenger service centre for NSL station

Wednesday, June 5, 2024

J113 & J115A - Nanyang Gateway, Nanyang Crescent & Peng Kang Hill update Q1 2024

A view of the 3 NTU stations part of the JRL's phase 3 northern section as at end-Q1 2024.

To complete our Q1 updates of the Jurong Region Line (JRL), we're at Nanyang Technological University (NTU) where the line's northern section of phase 3 is located. Consisting of 2 contracts covering 3 stations, this section was awarded entirely to Hwa Seng Builders, greatly simplifying the works required by using only a single contractor for the entirety of the works. Equipment can be shared and the contractor can better control construction traffic entering & exiting the university.

Wednesday, May 29, 2024

J112 - Jurong Hill & Jurong Pier update Q1 2024

 

21 March 2024 - Bored piling and sheet pile installation work at Jurong Hill station site in
end-Q1.

21 March 2024 - A view southwards of the Jurong Pier station in end-Q1.

Continuing on with our Q1 update of phase of the Jurong Region Line (JRL), we come to contract J112. This contract involves the construction of 2 stations at Jurong Hill and Jurong Pier, a road underpass connecting Jalan Boon Lay and Jurong Pier Road & associated JRL viaducts. We take a deeper look at the progress made over the first quarter in this post.

Friday, May 24, 2024

JRL - A snapshot in May 2024

Overview of JRL stations JS1 - JS8 as of May 2024.
Top (L - R): JS1 - Choa Chu Kang, JS2 - Choa Chu Kang West, JS2A - Forest Hill
Middle (L - R): JS3 - Tengah, JS4 - Hong Kah, JS5 - Corporation
Bottom (L - R): JS6 - Jurong West, JS7 - Bahar Junction, JS8 - Boon Lay

Overview of JRL stations JW1 - JW2 & JE1 - JE7 as of May 2024.
Top (L - R): JW1 - Gek Poh, JW2 - Tawas, JE1 - Tengah Plantation
Middle (L - R): JE2 - Tengah Park, JE3 - Bukit Batok West, JE4 - Toh Guan
Bottom (L - R): JE5 - Jurong East, JE6 - Jurong Town Hall, JE7 - Pandan Reservoir


Overview of JRL stations JW3 - JW5 & JS9 - JS12 as of May 2024.
Top (L - R): JS9 – Enterprise, JS10 – Tukang, JS11 – Jurong Hill
Middle (L - R): JS12 – Jurong Pier, JW3 – Nanyang Crescent, JW4 – Nanyang Gateway 
Bottom (L - R): JW5 – Peng Kang Hill, Contract J101 Tengah depot, Contract J120 Jurong East ITH

May has been a busy month for the various contracts of the Jurong Region Line (JRL). Each of the contracts has seen progress made with things beginning to pick up speed over at phase 1 of the line. Some changes are more visible than others and we're here to provide you with an extensive low-down of all the progress made. Loads of images after the jump for this month's update.

Wednesday, May 22, 2024

J111 - Enterprise & Tukang update Q1 2024

 

21 March 2024 - A view northwards along Jalan Boon Lay of the southern approach to
Enterprise station in end-Q1.

21 March 2024 - A view northwards along Jalan Boon Lay of the Tukang station site in end-Q1.

Phase 3 of the Jurong Region Line (JRL) is probably one of the least inspiring sections due to its remote location in serving largely industrial areas. Nonetheless, we'll breeze through an update on this section for you to get an idea of how works are coming along on the southern section. Kicking off our phase 3 updates for Q1 2024 is none other than contract J111 for the construction of Enterprise and Tukang stations. Thus far, all the action seems to be taking place at Enterprise station with the viaduct pier columns becoming visible here while Tukang station still tackles bored piling works - rather, well, boring.

Wednesday, May 15, 2024

J110 & J120 - Jurong East & ITH update Q1 2024

 

18 March 2024 - A view of Jurong East station as at end-Q1 2024.

18 March 2024 - A view of the contract J120 viaducts as at end-Q1 2024.

The section of Jurong Region Line (JRL) near Jurong East is being constructed under 2 contracts connected to contract J109 on either end. Jurong East station is being built under contract J110 while the Jurong East Integrated Transport Hub (ITH) and associated viaducts are being built under contract J120. Through Q1 both contracts have seen the casting of various sections of the project under their care. We take a closer look at the progress made over Q1 in this update.