Wednesday, May 29, 2024

J112 - Jurong Hill & Jurong Pier update Q1 2024

 

21 March 2024 - Bored piling and sheet pile installation work at Jurong Hill station site in
end-Q1.

21 March 2024 - A view southwards of the Jurong Pier station in end-Q1.

Continuing on with our Q1 update of phase of the Jurong Region Line (JRL), we come to contract J112. This contract involves the construction of 2 stations at Jurong Hill and Jurong Pier, a road underpass connecting Jalan Boon Lay and Jurong Pier Road & associated JRL viaducts. We take a deeper look at the progress made over the first quarter in this post.

JS11 - Jurong Hill
The Jurong Hill station will sit in the road median of Jurong Pier Road just before the Jurong Pier flyover. Featuring side platforms, the station is likely to be similar in design as other JRL stations such as Jurong West or Gek Poh. Throughout the first quarter, bored piling works have been underway to create the piles that will support the station piers in the road median. Towards the end of the quarter, sheet pile installation works commenced as well. The sheet piles will serve to allow soil covering the tops of the piles to be excavated before the pier's pile cap can be constructed.

27 January 2024 - A view northwards along Jurong Pier Road to the site of the Jurong Hill
station in early-Q1.

27 January 2024 - Bored piling works in progress at the Jurong Hill station site in early-Q1.

27 January 2024 - Bored piling works in the road median in early-Q1.

27 January 2024

27 January 2024 - This section of the site will see the construction of the road underpass connecting
Jalan Boon Lay to Jurong Pier Road.

18 February 2024 - Bored piling at the Jurong Hill station site in mid-Q1.

18 February 2024 - Another view of the ongoing bored piling at Jurong Hill station in mid-Q1.

18 February 2024

18 February 2024

18 February 2024

21 March 2024 - Portions of diverted roadway en route to Jurong Pier station in end-Q1.

21 March 2024 - Work underway to cast a diverted abutment approach ramp for the Jurong Pier
flyover.

21 March 2024 - Sheet pile installation work underway at Jurong Hill station in end-Q1.

21 March 2024 - A view northwards along Jurong Pier Road in end-Q1.

21 March 2024 - A view southwards along Jurong Pier Road.

21 March 2024

21 March 2024

JS12 - Jurong Pier
Of the two stations under the contract, there is more action to be seen at the JRL's southern terminus. Concrete structures have begun emerging at the station site and with each passing month, more such structures get continually added. Roadworks were also performed in the vicinity of the Jurong Pier flyover to divert access along the abutment approach further east. This would allow for works on one of the viaduct piers to take place closer to the bridge's approach structure in the road median.

27 January 2024 - A view southwards to the Jurong Pier station site in early-Q1.

27 January 2024 - Rebar visible ahead of the casting of additional permanent structures for the
station.

27 January 2024

27 January 2024 - Large concrete blocks visible on site in early-Q1.

27 January 2024 - Excavation underway towards the southern end of the station in early-Q1.

27 January 2024 - Excavation pits for the station pier pile caps.

27 January 2024

27 January 2024

27 January 2024 - A view northwards along Jurong Pier Road. The bus stop was to be 
decommissioned and a temporary bus stop shelter placed further north to allow a replacement 
retaining wall to be constructed.

27 January 2024 - A view of works ongoing for the replacement retaining wall and the temporary
bus stop shelter in view.

18 February 2024 - A view southwards to the Jurong Pier station site in mid-Q1.

18 February 2024 - A view of the permanent concrete structures for the station.

18 February 2024

18 February 2024 - The footings of the station piers visible as of mid-Q1.

18 February 2024

18 February 2024 - Rebar columns became visible at the southern end of the station site.

18 February 2024

18 February 2024 - A view northwards along Jurong Pier Road, near the site where the replacement
retaining wall was being constructed.

18 February 2024

21 March 2024 - A view southwards to the Jurong Pier station site in end-Q1. A low concrete
wall can be seen, demarcating the station boundary.

21 March 2024 - A close up view of the station boundary wall. Columns of rebar can be seen
at intervals along the low wall.

21 March 2024

21 March 2024 - Scaffolding being installed along the low wall. This may support the casting
of the concourse slab level, slightly elevated above the level of the street.

21 March 2024 - Workers installing more rebar and scaffolding at the station site.

21 March 2024

21 March 2024 - Large sections of cast concrete awaiting the next phase of construction.

21 March 2024 - Progress at the southern end of the station site.

21 March 2024 - Work to backfill the excavated pier caps underway. Extraction of the sheet piles
was also taking place.

21 March 2024 - One of the columns for a station pier visible with the pier cap.

21 March 2024 - An excavation pit for the over run viaduct pier pile cap.

21 March 2024 - Tree felling works were undertaken parallel to the Jurong Pier flyover.

21 March 2024 - A view southwards along Jurong Pier Road, with work underway to connect
the Jurong Pier flyover via a widened abutment approach.

Contract J112 is chugging along at a leisurely pace with some progress to show by way of permanent structures taking shape at Jurong Pier station. Do stay tuned as we keep you updated in the next round of progress updates.

This post will also be available on Instagram & Facebook on 30 May 2024.

No comments:

Post a Comment