Saturday, December 6, 2025

JRL - A snapshot in November 2025

Overview of JRL stations JS1 - JS8 as of November 2025.
Top (L - R): JS1 - Choa Chu Kang, JS2 - Choa Chu Kang West, JS3 - Tengah
Middle (L - R): JS4 - Hong Kah, JS5 – Corporation, JS6 - Jurong West
Bottom (L - R): JS7 - Bahar Junction, JS8 - Boon Lay


Overview of JRL stations JW1 - JW2 & JE1 - JE7 as of November 2025.
Top (L - R): JW1 - Gek Poh, JW2 - Tawas, JE1 - Tengah Plantation
Middle (L - R): JE2 - Tengah Park, JE3 - Bukit Batok West, JE4 - Toh Guan
Bottom (L - R): JE5 - Jurong East, JE6 - Jurong Town Hall, JE7 - Pandan Reservoir


Overview of JRL stations JW3 - JW5 & JS9 - JS12 as of November 2025.
Top (L - R): JS9 – Enterprise, JS10 – Tukang, JS11 – Jurong HillJW3 - Nanyang Gateway
Middle (L - R): JS12 – Jurong Pier, JW3 – Nanyang Crescent, JW4 – Nanyang Gateway 
Bottom (L - R): JW5 – Peng Kang Hill, Contract J101 Tengah depot, Contract J120 Jurong East ITH

It's been a while since we've done a Snapshot feature for the Jurong Region Line (JRL), with the last being done in September 2025. Since then, we've had the chance to visit the various sites again after a brief hiatus in October (you know, life gets busy). Here are some of the highlights, each of which could be their own headline, from the month of November:

  • Completion of viaduct span construction for Phase 1
  • Commencement of noise barrier installation along Phase 1 reaches more locations
  • Roofing works commences along Phase 3 (South)
The first of these headlines is significant, as it means that rail laying works can commence across the entire Phase 1 of the line. In fact, this has largely commenced as you'll come to see later on. Viaduct span construction is still ongoing along various parts of Phase 2 and 3. In total, 9 contracts have completed viaduct span construction works from a total of 13, bringing completion by contract to approximately 69%.


With so much activity taking place and progress being made, we'll dive deeper into the short updates across the various phases.