Monday, March 17, 2025

J150 - Trackwork update Q1 2025

8 March 2025 - A sleeper-laying machine on the Jurong Pier-bound track near Hong Kah station.

Track laying and related installation works - referred to as Track Related Installation Programme (TRIP) - commenced on the Jurong Region Line (JRL)'s main line following the handover of sections of viaduct near the Tengah Junction by contract J102 in August 2024 to the trackworks contractor under contract J150. This represented the first contract where viaducts were handed over for TRIP purposes. TRIP works will encompass the laying of rails (both running rails and the third rail as well), cabling for communications, signaling infrastructure and platform screen gates among other components. For this post, we'll look specifically at the rail laying component as this is among the first activities to be initiated under TRIP works as locomotives and wagons will use the installed rails for subsequent installation activities.

Thursday, December 12, 2024

J108 / Tengah Plantation, Tengah Park & Bukit Batok West - A 2024 progress report

We've been on a journey re-looking back at the progress made through the year at the various Jurong Region Line (JRL) contracts. Thus far, we've gone through the phase 1 contracts, which you can view here:

Having completed the rotation of phase 1 contracts, we now venture into phase 2 territory. These stations will open a year later than their phase 1 counterparts and will serve a separate service on their own, unofficially called the eastern route, which consists of 7 stations. The first contract along this phase is Contract J108, which was awarded to a joint venture between McConnell Dowell & John Holland.


Milestones attained by this contract thus far have included the completion of casting all precast segmental boxes for viaducts, the commencement of roof frame installation works at two (2) stations and the commencement of linkbridges connecting to station exits at one (1) station. Of the phase 2 contracts, this one is slightly ahead of the others. More details after the jump.

Monday, August 26, 2024

J108 - Tengah Plantation, Tengah Park & Bukit Batok West update Q2 2024

An overview of contract J108 stations at Tengah Plantation (top), Tengah Park (middle) and
Bukit Batok West (bottom) as of end-Q2 in June 2024.

Over Q2, contract J108 has seen the stations at Tengah Plantation & Tengah Park continue to take shape. Work at Bukit Batok West has also began to speed up with the structure of the station becoming more visible as more station columns are cast. Viaduct construction work also pushed further into Tengah. while causing some road diversions, ultimately inching towards completion. Other developments were also made in completing the various spans using the launch gantries Rock Steady and Magnificent Mammoth. More information after the jump.

Wednesday, May 1, 2024

J108 - Tengah Plantation, Tengah Park & Bukit Batok West update Q1 2024

 

18 March 2024 - An aerial view of Tengah Plantation station in end-Q1 2024.

18 March 2024 - An aerial view of Tengah Park station in end-Q1.

18 March 2024 - A view of the Bukit Batok West station site in end-Q1.

Contract J108 is the first of two contracts that cover three stations each - the other being neighbouring contract J109 which we'll be covering in the following post. Over the first three months of the year, work has been chugging along with viaduct spans taking shape and the station buildings slowly being cast. We take a closer look at the three stations under this contract - Tengah Plantation, Tengah Park & Bukit Batok West - in greater detail after the jump.

Sunday, December 10, 2023

J108 - Tengah Plantation, Tengah Park & Bukit Batok West update Q3 2023

Stations under contract J108 as on 24 September 2023.

A lot has happened last quarter over at contract J108 which is for the construction of 3 phase two stations at Tengah Plantation, Tengah Park & Bukit Batok West. Also part of the package are viaducts from Tengah Junction, where the line diverges from the western route, up to the interface with contract J109 along the Pan Island Expressway (PIE), south of Bukit Batok town. In order to speed up the updates ahead of the year-end recap that we're in the midst of preparing, we're updating the rest of the line by contract. Head on past the jump for loads of pictures about the progress made over Q3 2023.

Monday, July 31, 2023

J108 - Tengah Plantation update Q2 2023

 

14 May 2023 - A view of the concourse slab that has been cast.
Source: LinkedIn

Having cleared our updates on the quicker-moving phase 1 of the Jurong Region Line (JRL), we're now starting our updates on the 7 stations that will form phase 2 of the line. The first of these is the hardest to reach - Tengah Plantation - which is sited in the middle of Plantation Crescent in Tengah new town. There is good news though, as the area is set to open up from around August with the home owners receiving their keys shortly. This means that the area will gradually become accessible in addition to having several vantage points from which the construction can be observed. We'll definitely be making use of these to bring you some updates.

Tuesday, July 25, 2023

J108 - Second launch gantry

 

24 July 2023 - The second launch gantry for contract J108 raised into position south of Tengah
Park station to begin work.
Source: LinkedIn

Yesterday, the second launch gantry for contract J108 was raised into position south of Tengah Park station. The gantry will begin work assembling the viaduct spans for the cripple siding located here. The lifting process utilised 2 mobile crane units that lifted the gantry in a process known as a tandem lift. Once elevated to the desired height, the cranes swung the gantry over to the final position atop the supports and the gantry was locked in place.

Sunday, January 15, 2023

J108 - Tengah Plantation coming up

9 January 2023 - The concourse level crosshead wrapped in blue construction netting.

 Tengah Plantation station under contract J108 is one of the quickly up and coming stations on the Jurong Region Line (JRL). As of 9 January 2023, the crossheads for the concourse level are being constructed along with some columns that will support the track beds. During the recent ground breaking & viaduct construction segment launching ceremony held by the Land Transport Authority (LTA) on 13 January 2023, several images were released showing several cross sections of the JRL stations. One design in particular, shows a station within a road median - similar to the design that will be used at Tengah Plantation station.

Tuesday, December 27, 2022

J108 - Tengah Plantation & Park year-end review

 

11 December 2022 - An overview of Tengah Plantation station.

11 December 2022 - An overview of Tengah Park station.

Contract J108 is for the construction of 3 stations on the Jurong Region Line (JRL), however we will only be covering the 2 stations within Tengah for this contract in this post. No worries, the next station will be covered in the following post so no losing out there. While contract J108 may fall under the second phase of the line, works at this contract are progressing at lightning speed.

Wednesday, November 2, 2022

J108 - Tengah Plantation casting

 

30 October 2022 - An aerial view of the Tengah Plantation station.

Tengah Plantation station under contract J108 has been progressing steadily since we found a good vantage point from which to view the station earlier this year in June. From this viewpoint, we have been able to document the station's piers going up from mere rebar to concrete structures that are now progressing to have the concourse level crossheads cast.

Tuesday, August 23, 2022

JRL2 - Station renders

 

A new render of Bukit Batok West station under contract J108.
Source: LTA & John Holland-McConnell Dowell JV

We hope that you've enjoyed our previous post on the renders of the phase 1 stations of the Jurong Region Line (JRL). We're back with more now, this time for phase 2 which will run towards mega-hub Jurong East and onwards to the Pandan Reservoir.

Tuesday, June 28, 2022

Launch gantries on site

 

19 June 2022 - An aerial view of contract J108. Completed piers near Tengah Park station, Tengah
Plantation station and the Tengah junction in neighbouring contract J102 can be seen.

As construction work along the Jurong Region Line (JRL) progresses with several piers completed at contact J108 near Tengah Park, contactors John Holland & McConnel Dowell are preparing for the next phase of works. Spotted on site were the truss frames for a launch gantry.

Wednesday, February 2, 2022

CNY Special - First viaduct piers for JRL

 

01 February 2022 - Rebar visible above the hoarding for Jurong Region Line's viaduct piers.

We'd like to wish all our readers a Happy & Prosperous Lunar New Year! May each of you be blessed with bountiful fortune in the year of the Tiger. And to all the contractors on the Jurong Region Line (JRL) project, may you all experience good health (and safety) this coming year.

Through the Chinese New Year period, we have been travelling around a fair bit and noticed the first viaduct piers for the line beginning to emerge above the hoarding protecting the worksite.

Thursday, October 7, 2021

J108 Construction Update - Q3 2021

25 September 2021 - A view of the route as the line swings in to Tengah estate as seen from Bukit Batok Road.

Phase 2 of the Jurong Region Line (JRL) is the final phase we cover in our update for Quarter 3 of 2021. This phase consists of 4 contracts - J108, J109, J110 and J120 for the construction of various parts of viaducts and stations. Contract J108 was won by John Holland-McConnell Dowell and will connect phase 2 to the rest of the line at phase 1's Tengah interchange station. The contract will involve the construction of 3 stations at Tengah Plantation, Tengah Park & Bukit Batok West.

As this post is rather photo-heavy, we have decided to break the post up according to contract for easier readability. Do look out for our subsequent posts on other sections of the line.

Thursday, April 9, 2020

Contract updates - J108 & J111

Artist's impression of Bukit Batok West station
Source: McConnell Dowell
The Land Transport Authority (LTA) awarded Contract J108 for the construction of Tengah Plantation, Tengah Park & Bukit Batok West stations to a joint venture of McConnell Dowell and John Holland last month. This represents the first contract from phase 2 of the Jurong Region Line (JRL) to be awarded.

Monday, August 5, 2019

JRL2 - All contracts released for bid

The Land Transport Authority released the last tender for phase 2 of the Jurong Region Line (JRL) on 31st July 2019 - contract J109 for the design & construction of Toh Guan, Jurong Town Hall and Pandan Reservoir stations, viaducts inclusive. With the release of tender bidding for contract J109, all contracts for phase 2 of the line have been floated for tender.



Monday, March 4, 2019

Pre-Construction - Tengah, Hong Kah & Tengah Plantation

Being built as a new township, Tengah estate will see several Jurong Region Line stations serving the different districts within the town. Tengah station is to be located at the town centre, Hong Kah station will serve the southern portion while Tengah Plantation station serves the plantation residential district. In future, another station may be added further north between Tengah and Choa Chu Kang West stations to serve the north eastern portion of the town. All of these stations lie within a currently heavily vegetated area and works are underway to clear the area for construction activities to commence on the new town.

Station locations within Tengah New Town.
Source: LTA

Friday, May 11, 2018

2028 MRT & LRT system map

The MRT and LRT system map with the inclusion of the Jurong Region Line.
Source: Today
In case you were wondering how the Jurong Region Line would fit into the overall MRT & LRT system map, have a look for yourself. The map will be joined by the upcoming Cross Island Line and other future lines which the Land Transport Authority in currently studying. In addition, we get a first look at how the Jurong Region Line stations may look in the years to come.

Tengah Plantation station artist impression.
Source: Today

Monday, September 5, 2016

Roads JRL may align with - Jurong East branch

Typical road name sign
Source: SRX
In our previous post, we touched on the location shift of Choa Chu Kang bus interchange to make way for the Jurong Region Line (JRL) station. In this post, we explore the potential roads that the JRL may align with along the Jurong East & West Coast branch.