| Artist's impression of Bukit Batok West station Source: McConnell Dowell |
Thursday, April 9, 2020
Contract updates - J108 & J111
Tuesday, February 18, 2020
Contract awards - J151, J106, J107 & J110
![]() |
| Render of the contract J151 trains by Hyundai Rotem. Source: LTA |
Tuesday, December 10, 2019
Contract awards - J101 & J105
![]() |
| Concept design options for Tengah Depot. Source: LinkedIn |
Thursday, September 12, 2019
Contract awards - J102 & J103
The Land Transport Authority (LTA) announced the awards of contracts J102 and J103 for the Jurong Region Line (JRL) on 10th September 2019. Contract J102 comprises of 3 stations - Choa Chu Kang interchange, Choa Chu Kang West & Tengah interchange. On the other hand, contract J103 comprises of 2 stations - Hong Kah & Corporation.
![]() |
| Contract boundaries for J102 & J103. Source: LTA |
Wednesday, September 4, 2019
JRL3 - Tender process begins & J106 update
On 30 August 2019, the Land Transport Authority kicked off the tendering process for the third and final phase of the Jurong Region Line. Contract J113 for the design and construction of Nanyang Gateway and Nanyang Crescent stations with associated viaducts was released for tender. With a tentative closing date of 20 December 2019, interested parties that have been pre-qualified will have approximately 4 months to submit bids for the project. The deadline for submissions, however, is likely to be extended based on experience with other similar contracts. Contract J113 is due for completion by 30 December 2027, in time for the JRL's phase 3 operations in the following year, 2028.
Monday, August 5, 2019
JRL2 - All contracts released for bid
The Land Transport Authority released the last tender for phase 2 of the Jurong Region Line (JRL) on 31st July 2019 - contract J109 for the design & construction of Toh Guan, Jurong Town Hall and Pandan Reservoir stations, viaducts inclusive. With the release of tender bidding for contract J109, all contracts for phase 2 of the line have been floated for tender.
Monday, July 29, 2019
J105 - Tender closed
Contract J105 entails the construction of Jurong West and Bahar Junction stations along with associated viaducts on the Jurong Region Line (JRL). The contract was first floated for tender in February and closed last week on 25 July 2019. A total of 4 companies responded by placing bids for the contract.
![]() |
| List of companies bidding for contract J105. Source: LTA |