24 June 2024 - A view of Choa Chu Kang & Choa Chu Kang West stations under contract J102 as of end-Q2. |
A lot has taken place in Q2 for contract J102. With 4 stations being built under the contract, we had to split this update into 2 parts to make it more bite-sized and not an overload of information or more of a huge photo dump than it already is. Progress has been swift and moving full steam ahead as the changes to the sites can be seen with every visit. Nonetheless, it will still take some time before the Jurong Region Line (JRL) sections under this contract can achieve basic structural completion.
JS1 - Choa Chu Kang
Over at Choa Chu Kang station, several of the viaduct piers that will support the terminus' crossover have taken shape. The station itself has also seen the casting of the platform level commence. Works had progressed sufficiently that a row of hoarding was set up as a temporary protective enclosure for trains running on the southbound track of the North-South Line (NSL).
|
20 April 2024 - An aerial view of Choa Chu Kang station in early-Q2. |
|
22 May 2024 - An aerial view of Choa Chu Kang station in mid-Q2. |
|
24 June 2024 An aerial view of Choa Chu Kang station in end-Q2. |
|
2 June 2024 - A view of the Choa Chu Kang station with JRL expansion on the left. |
|
20 April 2024 - A view of the existing North-South Line (NSL) station platform in early-Q2. Construction netting is in place next to the southbound trackway. |
|
22 May 2024 - A view of the NSL platform with hoarding since gone up along the southbound trackway in mid-Q2. |
|
22 May 2024 - Another view of the hoarding put in place along the live, operational track. |
At the northern end of the station, a former atrium that was previously hoarded off since Q3 2023 saw the hoarding finally come down. Hacking work took place to enlarge the atrium while other parts of it were slabbed over to allow a staircase to connect to the transfer mezzanine level below. The new staircase will replace the existing up-riding escalator that will be demolished to reconfigure the station's vertical access.
You can read about the major modifications being done to the station here. |
22 May 2024 - A view of the hoarded up atrium in mid-Q2. |
|
22 May 2024 - JRL station works at the northern end of the station in mid-Q2. |
|
24 June 2024 - A view of the hoarding around the atrium that was since taken down by end-Q2. |
|
24 June 2024 - A view of the new staircase linking the NSL platform to the transfer mezzanine level below. Part of the atrium was slabbed over, while a portion of the existing platform beneath the directional signs was hacked away to allow the staircase to be constructed. |
|
24 June 2024 - Former directional signage that pointed the direction of travel for either platform at the NSL station. The slab here was hacked away to fit in the new staircase. |
At the concourse level, major changes have progressed with the reconfiguration of the passenger circulation areas. Retiling has progressed, thankfully getting rid of the gaudy lime tiles formerly used at the station and replacing them with a standard shade of grey. Cladding work has also progressed with the new passenger service centre clearly visible, with mock signage placed up as well. New ceiling panels were also installed and unwrapped by the end of the quarter.
|
20 April 2024 - A view of works to renew and reconfigure the existing station concourse fare unpaid area. A relocated fare line will transform this area into a fare paid zone. |
|
20 April 2024 - Works include replacement of the existing tiles as well as alterations to the ceiling panels. New signage will replace the existing signage boxes eventually. |
|
20 April 2024 - A view of the new passenger service centre (PSC) for the NSL near Exit A as seen in early-Q2. |
|
20 April 2024 |
|
22 May 2024 - A view of the completed section of new tiling against the former station tiling as of mid-Q2. |
|
22 May 2024 - The taped boxes represent the location of the future relocated fare gates. |
|
22 May 2024 - A view of the new NSL PSC as of mid-Q2. |
|
22 May 2024 - New ceiling panels were installed to refresh the look of the station. |
|
2 June 2024 - New tactile floor guides installed ahead of the relocation of the existing fare line as of end-Q2. |
|
2 June 2024 - Cladding beginning to go in for the new NSL PSC. |
|
2 June 2024 - Ongoing works to replace the tiles within the area at Exit A. |
|
2 June 2024 - One last look at the existing tiling near the ticket machines before the area is retiled. |
|
2 June 2024 |
|
24 June 2024 - A look at the nearly completed new NSL PSC. Mock signage is included to give the contractor & client an idea of how the final product will look. |
|
24 June 2024 - Cladding and glass installation at the new NSL PSC had been completed by end-Q2. |
|
24 June 2024 - A view into the new fare paid zone with escalators connecting the concourse level with the transfer mezzanine visible. The area beyond the hoarding is where the current up-riding escalator is located. In the next phase of works, this escalator will be demolished as part of station reconfiguration works. |
|
24 June 2024 - A view of the location of the new fare line post relocation. |
|
20 April 2024 - A view towards Exit B of the station fare unpaid concourse area in early-Q2. |
|
2 June 2024 - Progress of works to retile the area as of end-Q2. |
|
2 June 2024 - Works on the right are for the reconfiguration of the existing station area. |
|
2 June 2024 - Hoarding put up to begin the transformation process. |
|
2 June 2024 - A new fare line will be located here along the corridor towards Exit B. |
|
2 June 2024 - The section underneath the LRT platform 3 will remain as is. |
|
24 June 2024 - Progress of re-tiling works as at end-Q2. |
|
24 June 2024 - Some of the existing signage is hidden away by the new ceiling panels. Work to adjust these will be conducted eventually. |
|
24 June 2024 - The area where the relocated fare line will be now appears more complete. |
|
24 June 2024 |
|
24 June 2024 - A view of where the new and existing tactile floor guides will link up. |
Shops around Exit A and C at the permanent station appeared to be more complete by the end of the quarter. In preparation for the relocation of retail units to these permanent shops, several businesses have closed shop at the temporary units built to replace the former shops that needed to make way for the station's expansion.
|
20 April 2024 - The exterior of Exit A, which opens into the Lot 1 plaza, as seen in early-Q2. |
|
20 April 2024 - The exterior of Exit A while re-tiling works were underway. |
|
20 April 2024 - Works ongoing for fitting in the walls of the new NSL PSC. |
|
20 April 2024 - A view of the corridor towards the temporary retail shop units in early-Q2. |
|
22 May 2024 - A view of the exterior of Exit A as of mid-Q2. |
|
22 May 2024 - Cladding works underway at the new retail shops at Exit A. |
|
22 May 2024 - A view of the corridor towards the temporary retail shop units in mid-Q2. New tiles were since installed while work on the retail units had progressed. |
|
22 May 2024 - A view of one of the new retail units. |
|
2 June 2024 An exterior view of Exit A in end-Q2. |
|
2 June 2024 - A view of the corridor towards the temporary retail shop units in end-Q2. |
|
24 June 2024 - An exterior view of Exit A as of end-Q2. |
|
24 June 2024 - Completed cladding works and a new sign installed are visible. |
|
24 June 2024 - Looking towards the new retail units along the corridor. |
|
24 June 2024 - A view of businesses shuttered as the temporary retail units will soon be torn down. |
|
24 June 2024 - The corridor within the temporary facility had grown more empty as businesses began relocating one by one. |
|
24 June 2024 |
|
24 June 2024 - Another view of the new retail units at Exit A. |
Viaduct construction work saw the completion of several piers on both the northern and southern ends of the station building. Most notable progress was seen at the pair of piers that will support the line's crossover tracks, just to the south of the station. These piers were cast with the supporting crossheads also making their appearances. Further south, viaduct segment launching continued with a section of approximately 2.5 spans being completed.
|
20 April 2024 - Viaduct piers to the north of the station building in early-Q2. |
|
22 May 2024 - A view of the viaduct piers immediately north of the station in mid-Q2. |
|
22 May 2024 - Viaduct piers on either side of Choa Chu Kang Loop. |
|
22 May 2024 - The final pier of the JRL north of Choa Chu Kang station. |
|
20 April 2024 - The crosshead for 1 of 5 piers that will eventually support the line's crossover tracks being cast in early-Q2. |
|
20 April 2024 - Formwork installation ahead of casting works for the pier's crosshead. |
|
20 April 2024 - Rebar and stress tendon works ongoing for the viaduct pier crosshead before concrete is poured in as part of the casting process. |
|
20 April 2024 - The second pier having its portal beam installed. |
|
22 May 2024 - A view of the pair of viaduct piers, one with a completed crosshead and another with a completed portal beam in mid-Q2. |
|
22 May 2024 - A close up view of the two viaduct piers in mid-Q2. |
|
22 May 2024 |
|
22 May 2024 - An aerial view of the construction progress of the viaduct piers. |
|
24 June 2024 - An aerial view showing the viaduct piers under construction in end-Q2. The second pier was having its crosshead cast. |
|
24 June 2024 - Rebar and formwork installation ongoing for the crosshead casting. |
|
20 April 2024 - A view of the completed section of viaduct span. Work was ongoing for the portal pier for the next span as of early-Q2. |
|
20 April 2024 - Another view of the completed viaduct spans. |
|
20 April 2024 - The 2 completed viaduct spans seen from street level as of early-Q2. |
|
20 April 2024 |
|
20 April 2024 - This movement & expansion joint pier adopts a design similar to the existing NSL viaduct. |
|
22 May 2024 - Progress of works for the portal pier near the carpark entrance as of mid-Q2. |
|
22 May 2024 |
|
22 May 2024 |
|
22 May 2024 - Scaffolding was set up at the end of the completed span for viaduct segment launching towards the movement & expansion joint pier. |
|
22 May 2024 |
|
22 May 2024 |
|
2 June 2024 - A view of the completed viaduct spans as of end-Q2. |
|
2 June 2024 - The viaduct span now connects to the movement & expansion joint pier. |
|
2 June 2024 - Epoxy yet to be applied to bond the segments with the existing span. |
|
24 June 2024 - The first pier column for the portal pier is now visible. |
|
24 June 2024 |