J108 - Tengah Plantation, Tengah Park & Bukit Batok West update Q2 2024

An overview of contract J108 stations at Tengah Plantation (top), Tengah Park (middle) and
Bukit Batok West (bottom) as of end-Q2 in June 2024.

Over Q2, contract J108 has seen the stations at Tengah Plantation & Tengah Park continue to take shape. Work at Bukit Batok West has also began to speed up with the structure of the station becoming more visible as more station columns are cast. Viaduct construction work also pushed further into Tengah. while causing some road diversions, ultimately inching towards completion. Other developments were also made in completing the various spans using the launch gantries Rock Steady and Magnificent Mammoth. More information after the jump.

Monday, August 19, 2024

JRL - A snapshot in August 2024

Overview of JRL stations JS1 - JS8 as of August 2024.
Top (L - R): JS1 - Choa Chu Kang, JS2 - Choa Chu Kang West, JS2A - Forest Hill
Middle (L - R): JS3 - Tengah, JS4 - Hong Kah, JS5 - Corporation
Bottom (L - R): JS6 - Jurong West, JS7 - Bahar Junction, JS8 - Boon Lay


Overview of JRL stations JW1 - JW2 & JE1 - JE7 as of August 2024.
Top (L - R): JW1 - Gek Poh, JW2 - Tawas, JE1 - Tengah Plantation
Middle (L - R): JE2 - Tengah Park, JE3 - Bukit Batok West, JE4 - Toh Guan
Bottom (L - R): JE5 - Jurong East, JE6 - Jurong Town Hall, JE7 - Pandan Reservoir


Overview of JRL stations JW3 - JW5 & JS9 - JS12 as of August 2024.
Top (L - R): JS9 – Enterprise, JS10 – Tukang, JS11 – Jurong HillJW3 - Nanyang Gateway
Middle (L - R): JS12 – Jurong Pier, JW3 – Nanyang Crescent, JW4 – Nanyang Gateway 
Bottom (L - R): JW5 – Peng Kang Hill, Contract J101 Tengah depot, Contract J120 Jurong East ITH

August has been a busy month for the Jurong Region Line (JRL) with several milestones being achieved. Contract J102 saw the handover of completed viaduct spans to trackworks contractor under contract J150 and contract J109 saw the lifting of the launch gantry for viaduct construction at Jurong Town Hall's station site. In addition, roof frame installation works were ongoing at Hong Kah (JS4), Corporation (JS5) and Jurong West (JS6) stations. More details on the progress made at the various sites after the jump.

Thursday, August 15, 2024

J102 & J150 - Handover of completed viaducts at Tengah for track works

 

A view of the completed viaduct spans for the main line (west route: Choa Chu Kang - Jurong
Pier - Peng Kang Hill) and the non-revenue service connection track at Tengah Junction.
Source: LinkedIn

A milestone moment has been reached in the construction of the Jurong Region Line (JRL). A section of the under construction viaducts in Tengah have been successfully handed over to trackworks contractor China Railway First Group this week. This section of viaducts, under contract J102 by Shanghai Tunnel Engineering Co, has seen the installation of cable racks, cable troughs and first stage concreting before the handover was effected.

Tuesday, August 13, 2024

J107 - Gek Poh & Tawas update Q2 2024

A view of contract J107 stations at Gek Poh and Tawas in end-Q2.

Advances in the progress of Gek Poh and Tawas stations were seen over Q2 of the year. At Gek Poh station, the concourse was largely completed while over at Tawas, the platform level beams were coming along well. Viaduct progress along contract J107 was also making headway, with viaduct spans stretching longer and longer through the quarter. Join us as we dive into the progress update for the contract over the second quarter of 2024.

Wednesday, August 7, 2024

J106 - Boon Lay update Q2 2024

16 June 2024 - An aerial view of the new JRL station building and viaducts of contract J106.

Contract J106 for the construction of Boon Lay station and viaducts for the Jurong Region Line (JRL) has seen steady progress at its site through Q2 of the year. Through the quarter, the station building has continued to take shape with the structure rising from the concourse level on the third floor to the platform level on the fourth floor. Eventually, both halves of the station to the north and south of the existing East-West Line (EWL) viaduct will meet above the operational line.

Sunday, August 4, 2024

J105 - Jurong West & Bahar Junction update Q2 2024

A view of the Jurong West (top) and Bahar Junction (bottom) stations under contract J105 as
of end-Q2.

Along phase 1, contract J105 is without a doubt one of the most interesting contracts to observe, given that it encompasses the construction of the unique Bahar Junction station. Also included under the contract is the more tame and templated Jurong West station. Over the past quarter, gains have been made in both stations' construction. The viaducts along the stretch were also coming together as well, with sections of completed spans progressing to the next stage of construction.

Thursday, August 1, 2024

J103 - Hong Kah & Corporation update Q2 2024

Hong Kah & Corporation stations as seen in end-Q2.

Contract J103 has seen some of the greatest progress in station construction while at the same time, the slowest of viaduct progress among the first phase of the Jurong Region Line (JRL). Over the past quarter, Corporation station has emerged as the most complete along the line while Hong Kah's stagnated progress has finally made some headway. The viaducts however, were still far from completion - a critical component of the line and its operation, given that the viaducts under the purview of the contract also connect the main line with the depot. We'll explore the progress made under the contract over Q2 in greater detail after the jump - do be fair warned, this post is highly picture-intensive.