Friday, May 24, 2024

JRL - A snapshot in May 2024

Overview of JRL stations JS1 - JS8 as of May 2024.
Top (L - R): JS1 - Choa Chu Kang, JS2 - Choa Chu Kang West, JS2A - Forest Hill
Middle (L - R): JS3 - Tengah, JS4 - Hong Kah, JS5 - Corporation
Bottom (L - R): JS6 - Jurong West, JS7 - Bahar Junction, JS8 - Boon Lay

Overview of JRL stations JW1 - JW2 & JE1 - JE7 as of May 2024.
Top (L - R): JW1 - Gek Poh, JW2 - Tawas, JE1 - Tengah Plantation
Middle (L - R): JE2 - Tengah Park, JE3 - Bukit Batok West, JE4 - Toh Guan
Bottom (L - R): JE5 - Jurong East, JE6 - Jurong Town Hall, JE7 - Pandan Reservoir


Overview of JRL stations JW3 - JW5 & JS9 - JS12 as of May 2024.
Top (L - R): JS9 – Enterprise, JS10 – Tukang, JS11 – Jurong Hill
Middle (L - R): JS12 – Jurong Pier, JW3 – Nanyang Crescent, JW4 – Nanyang Gateway 
Bottom (L - R): JW5 – Peng Kang Hill, Contract J101 Tengah depot, Contract J120 Jurong East ITH

May has been a busy month for the various contracts of the Jurong Region Line (JRL). Each of the contracts has seen progress made with things beginning to pick up speed over at phase 1 of the line. Some changes are more visible than others and we're here to provide you with an extensive low-down of all the progress made. Loads of images after the jump for this month's update.

Phase 1
The first section of the line is approximately 3 years away from completion. Contracts under this phase of the line are quickly completing viaduct spans, pushing stations up to the platform levels and beginning with the installation of the parapet walls along the viaducts. A lot of work still remains before the track laying and cable works can begin.

Tengah depot (Contract J101)
In a nutshell: The depot is fighting against the clock with the civil works still underway for the workshops and stabling yard. These key sections are essential for the delivery of the first J151 train sets. According to the Land Transport Authority (LTA), these trains were expected to arrive in the middle of the year. However judging by how complete the depot is, it appears that this may not be likely. We're betting that 2025 might be a better bet. Trackwork has been ongoing just outside the workshops and has recently begun outside the stabling yards. No rails here yet, but sleepers and ballast can be seen there.

1 May 2024

1 May 2024

1 May 2024

1 May 2024

1 May 2024

23 May 2024

23 May 2024

JS1 - Choa Chu Kang (Contract J102)
In a nutshell: Work at the station has seen the installation of hoarding alongside the existing North-South Line viaduct as construction of the new platform begins. The trackbeds for the JRL station are now well established with the JRL platform taking shape. Work is still underway on several viaduct piers near the station even as viaduct span construction south of the station continues. Within the existing NSL station concourse, the old flooring is being replaced with new tiles (thank goodness we got rid of the horrendous lime tiles) ahead of the major revamp of the fare-paid areas.

22 May 2024

22 May 2024

22 May 2024

22 May 2024

22 May 2024

22 May 2024

JS2 - Choa Chu Kang West (Contract J102)
In a nutshell: Viaduct span construction has recently kicked off along Choa Chu Kang Avenue 3, along which the station is located. Works at the station have seen the completion of the concourse level columns, with casting for the plant and back-of-house rooms taking place. Beams to support the platform level were also being cast.

22 May 2024

22 May 2024

22 May 2024

22 May 2024

22 May 2024

22 May 2024

JS2A - Forest Hill (Contract J102, provisional future station)
In a nutshell: The major change near the future station would be the completion of segment launching works on the Tengah-side of the special span across Brickland Road. Segment launching works have recently commenced on the Choa Chu Kang-side and will shortly bridge the gap over the road junction.

22 May 2024

22 May 2024

22 May 2024

JS3 - Tengah (Contract J102)
In a nutshell: Progress at the elusive station seems to centre around both launch gantries closing in on either side. Gantry Mulan works the lower level while gantry Gaia works the upper level. The viaduct spans leading to the station near the Tengah junction where the east and west routes diverge has also seen parapet installation works commence. This is likely a pre-cursor to trackwork installation commencing shortly as the parapet walls also include brackets for cabling.

23 May 2024

23 May 2024

23 May 2024

JS4 - Hong Kah (Contract J103)
In a nutshell: At long last Hong Kah station is progressing further upwards. Work has recently commenced on casting of the platform level beams atop the concourse level columns. These will aid in providing the horizontal support underneath the platform and trackbeds. Viaduct pier construction west of the station has also made progress although there is still a significant amount of empty space to be filled with viaduct piers.

23 May 2024

23 May 2024

23 May 2024

JS5 - Corporation (Contract J103)
In a nutshell: Arguably one of the most advanced stations in terms of overall completeness, roof truss installation continued at Corporation. Each side of the station will see the installation of 7 V-shaped columns that work to support the roof above. To date, 5 of the pairs have been installed, leaving 2 further pairs to completion. Casting work for the plant rooms on the western end of the platform have begun with the installation of rebar.

1 May 2024

1 May 2024

1 May 2024

23 May 2024

23 May 2024

23 May 2024

JS6 - Jurong West (Contract J105)
In a nutshell: Jurong West station has seen the beginning of its trackbeds forming, with rebar work taking place ahead of the parapet wall casting. The design of the station here calls for a slightly different design, where the trackbeds are supported by two beams beneath as opposed to being fully trough-like. Give the station a few more weeks and we'll be able to see the trackbed sections in their full glory. Viaduct span construction has also seen the installation of segments on the second truss completed. Further adjustments of the individual segments will be done before they are tensioned and bonded together.

1 May 2024

1 May 2024

1 May 2024

23 May 2024

23 May 2024

23 May 2024

JS7 - Bahar Junction (Contract J105)
In a nutshell: Launching works at Bahar Junction's satellite station building have continued, with the station's concourse beam segments now suspended in mid-air for a fair distance. This is, undoubtedly, one of the most unique methods of constructing a station locally. Never before has a station required segment launching for its concourse level. Progress continues to be made with the various portal piers taking shape and viaduct spans gradually growing longer. Work at the main station building has also reached the platform level.

23 May 2024

23 May 2024

23 May 2024

23 May 2024

23 May 2024

23 May 2024

JS8 - Boon Lay (Contract J106)
In a nutshell: Work at Boon Lay station begins on the tricky part - constructing over the existing East-West Line (EWL) viaduct. This will see both sides of the station come together one level above the EWL. Connecting these two halves of the station will not be an easy task, owing to the limited window in which work can take place to prevent disruption to the existing rail service. Further north of the station, work has begun on the painstaking process of launching viaduct segments that will see spans completed atop the movement expansion joint piers. Near the contract boundary with J105, parapet wall installation work has also recently begun.

1 May 2024

1 May 2024

1 May 2024

12 May 2024

12 May 2024

JW1 - Gek Poh (Contract J107)
In a nutshell: All 10 pairs of concourse level arms have been successfully installed over at Gek Poh station and the supporting frames since removed. Casting work for some of the viaduct columns in the middle of the station continues, now that there is a deck where formwork has be installed upon.

23 May 2024

23 May 2024

23 May 2024

23 May 2024

JW2 - Tawas (Contract J107)
In a nutshell: Work continues at the station with platform sections being installed. Further west, the viaduct span creeps closer to the station as does a section of viaduct connecting to the special crossing over the Pan Island Expressway to Gek Poh.

16 May 2024

16 May 2024

16 May 2024

16 May 2024

Phase 2
The next section of the line is still several years away. However, the contractors on this section of the line are not slacking off either with decent progress being made at several sites along the phase.

JE1 - Tengah Plantation (Contract J108)
In a nutshell: Construction of the platform level and trackbeds is in full swing. Unlike several stations in phase 1, the platform level is mostly made out of beams for now with the slab flooring not yet cast. The rough shape of the station's platform can be seen nonetheless. Viaduct span construction continues along Plantation Crescent.

22 May 2024

22 May 2024

22 May 2024

22 May 2024

22 May 2024

JE2 - Tengah Park (Contract J108)
In a nutshell: The station building is in somewhat of a mixed progress with half of the station commencing on platform beam  casting. The remaining half has yet to begin casting of these structures. Viaduct span construction is almost complete for the sections on either side of the station with parapet wall construction beginning to the station's south. To the north, a traction substation is likely to be built next to the Tengah electrical sub station facility.

22 May 2024

22 May 2024

22 May 2024

22 May 2024

22 May 2024

22 May 2024

JE3 - Bukit Batok West (Contract J108)
In a nutshell: Station piers for half of the station's full structure have taken shape at street level. The remaining half will be gradually completed. Works on the viaduct piers still continues as well, east of the station building.

1 May 2024

1 May 2024

1 May 2024

1 May 2024

1 May 2024

JE4 - Toh Guan (Contract J109)
In a nutshell: Work at the station has seen the installation of formwork for the concourse slab's crossheads. Station piers are progressively appearing as well with the columns being cast before crosshead construction can proceed. Viaduct segment launching has seen the lifting frames shifted onto another pier to begin the process so that the viaduct section that abuts the movement expansion joint pier built by contract J108 can be completed and the pier handed back to the neighbouring contractor.

1 May 2024

1 May 2024

1 May 2024

1 May 2024

Tracks through Jurong East Integrated Transport Hub (Contract J120)
In a nutshell: Formwork installation for the second span has been completed ahead of casting work. The next few viaduct piers have also begun to take shape.

1 May 2024

1 May 2024

1 May 2024

JE5 - Jurong East (Contract J110)
In a nutshell: Installation of formwork for the concourse level slab has begun at the western end of the station. Scaffolding has also been installed at the eastern end of the station, signifying the commencement of similar works at this end of the station too. Over at the station plaza, work on the street-level footings has been completed and the structure should begin to rise shortly.

1 May 2024

1 May 2024

1 May 2024

1 May 2024

1 May 2024

JE6 - Jurong Town Hall (Contract J109)
In a nutshell: Work at the station is still centred on the concourse slab level. The viaduct piers in the vicinity still only consist of the pier columns, with no crossheads cast as yet.

1 May 2024

1 May 2024

1 May 2024

1 May 2024

JE7 - Pandan Reservoir (Contract J107)
In a nutshell: Similar to Jurong Town Hall station's progress, not much appears to have changed at Pandan Reservoir. The station structure is still focused on street-level works while the viaduct piers only exist as columns with no crossheads yet.

1 May 2024

1 May 2024

1 May 2024

1 May 2024

1 May 2024

Phase 3 (South)
Some of the viaduct piers along the southern stretch of phase 3 appear to be more complete than some of those along phase 2 of the line. Nonetheless, there are still wide stretches devoid of any piers - be it viaduct or station.

JS9 - Enterprise (Contract J111)
In a nutshell: Viaduct piers on either side of the station have taken place although the piers for the station itself have not come up as quickly. Crosshead casting has been completed for some of the viaduct piers near Jurong Central Park, with segment launching underway.

1 May 2024

1 May 2024

1 May 2024

23 May 2024

JS10 - Tukang (Contract J111)
In a nutshell: Work is still underway on the station's foundation which will support the station piers in the road median. Do pardon the less than clear shots as the weather simply refused to cooperate with us during our visit to the site.

12 May 2024

12 May 2024

12 May 2024

JS11 - Jurong Hill (Contract J112)
In a nutshell: Similar to Tukang station, work is underway on the station's bored piles which will support the piers in the road median. Once again, apologies for the slightly less clear images due to the weather.

12 May 2024

12 May 2024

12 May 2024

JS12 - Jurong Pier (Contract J112)
In a nutshell: Several more of the station's street-level structures can be seen. Thankfully, at the time of visit the weather had not begun unleashing its full fury as yet. The beginnings of the base of a few columns can be clearly seen at the station site.

12 May 2024

12 May 2024

12 May 2024

12 May 2024

12 May 2024

Phase 3 (North)
The final section of phase 3 to the north shows great progress. Viaduct segment launching works have been underway for some time with significant sections completed. The stations though, are taking a bit longer to come about.

JW3 - Nanyang Gateway (Contract J113)
In a nutshell: Great headway has been made with the launching of viaduct segments outside Hall 8. Several more viaduct piers have also begun popping up along Nanyang Avenue. At the station site, the first of the station's pier columns are beginning to make an appearance.

1 May 2024

1 May 2024

1 May 2024

1 May 2024

1 May 2024

1 May 2024

1 May 2024

JW4 - Nanyang Crescent (Contract J113)
In a nutshell: Excavation work has finally unveiled the foundations of the station's lower concourse area. With the excavation reaching this base level, work on the station's structure can begin in earnest. A section of viaduct span just east of the station has been completed with viaduct pier casting continuing eastwards.

1 May 2024

1 May 2024

1 May 2024

1 May 2024

1 May 2024

JW5 - Peng Kang Hill (Contract J115A)
In a nutshell: The final contract of the line has seen noise barrier installation near the station site completed. Additionally, caissons that were dug now have the beginnings of the base of viaduct pier columns emerging.

1 May 2024

1 May 2024

1 May 2024

1 May 2024

A similar but consolidated (a.k.a. simplified) post will be available on Instagram & Facebook on 25 May 2024.