Pages

Monday, November 20, 2023

J103 - Corporation update Q3 2023

 

16 September 2023 - A view of progress at the station at the end of Q3 2023.

Hey there, thanks for putting up with the team being on vacation the last few days. It's been good to have a bit of a break and for the majority of the time we'd been on vacation had scheduled posts in our absence. But we're ready to get back into our regular quarterly updates and with an upcoming November snapshot in a few weeks' time, so do get ready for those.

Today we're looking at the progress made at contract J103's Corporation station. To date, the Land Transport Authority has not confirmed the station names or put them up for voting/suggestions as they had done with other lines previously. We're wondering if they will be doing the same for the Jurong Region Line (JRL) and Cross Island Line (CRL), or if they will ultimately simply decide on the names themselves. The last round where members of the public got to vote for or suggest station names was on the Circle Line stage 6 (CCL6) back in 2017 - 6 years ago.

Nonetheless, the lack of a confirmed station name has not hindered progress over at Corporation station's site. Over the past quarter, work has progressed to finish up the majority of the concourse slab with works beginning on the concourse level columns towards the end of the quarter. Viaduct piers on either side of the station were also in progress, with the viaduct segment launching taking place on the eastern side of the station. Preparation works were being undertaken ahead of the launching gantry's eventual installation atop the piers as well.


July 2023
In early-Q3, work was focused on building up the concourse level slab between the completed station piers. Further along, viaduct piers were being constructed near the exit ramp from the Pan Island Expressway (PIE) and along Jurong West Avenue 2.

15 July 2023 - A view westwards towards Jurong West Avenue 2. Construction is ongoing on
the left for the mainline viaduct.

15 July 2023 - Construction work in progress on the left of Jurong West Avenue 2.

15 July 2023 - Viaduct piers being built.

15 July 2023

15 July 2023 - The station site, currently on the left of Jurong West Avenue 2, will eventually be
located in the road median.

15 July 2023 - Concourse level slabs can be seen sitting on site prior to installation.

15 July 2023 - An aerial view of the progress of station construction in early-Q3 2023.

15 July 2023 - A close up view of the station structure. Some concourse level beams have been
installed while there are still gaps present.

15 July 2023

23 July 2023 - A view eastwards along Jurong West Avenue 2, with the station site on the right.

23 July 2023

23 July 2023 - Continued construction of the viaduct piers. The reception tracks towards the
Tengah Depot will diverge from the main line tracks here.

23 July 2023

23 July 2023 - Viaduct pier construction works continue along the exit ramp from the PIE.

August 2023
Construction at the station site was still focused on getting the beams installed for the concourse slab. At the viaduct sections, construction was still underway for additional piers while others were closer to completion with the casting of the crossheads completed. During this month, the Public Utilities Board (PUB) had to conduct urgent water mains rectification works at the junction between Corporation Road & Jurong West Avenue 2. As such, marshals were deployed to direct traffic at the increasingly complex junction.

6 August 2023 - Excavation pit for the casting of the pile cap of a viaduct pier near the PIE exit
ramp.

6 August 2023 - Several completed viaduct piers.

6 August 2023 - Viaduct piers and the start of the station building.

6 August 2023 - Lots of scaffolding in place to assist with casting the concourse level slab after
the installation of the precast beams. A layer of rebar and concrete is added on top to provide a
smooth continuous flooring for the concourse level.

6 August 2023 - Looking westwards along Jurong West Avenue 2 where the contract boundary
is located just ahead of Jurong West station.

13 August 2023 - An aerial view of the station progress.

13 August 2023 - Casting of the concourse level slab has been completed at this end, evidenced
by the removal of the scaffolding below.

13 August 2023 - Viaduct piers with completed crosshead casting east of the station.

13 August 2023 - A view of the station building from street level.

27 August 2023 - The junction between Corporation Road and Jurong West Avenue 2 was made
further complicated with Public Utilities Board repair work to water mains.

27 August 2023 - Viaduct pier getting ready for crosshead construction.

27 August 2023 - A view of the station building, with scaffolding removed from the first section.

27 August 2023

27 August 2023 - Pieces of a launch gantry observed on site.

27 August 2023 - The gantry will need to be assembled together and thereafter lifted up.

27 August 2023 - Progress of viaduct pier construction along the PIE exit ramp.

31 August 2023 - Viaduct piers have been cast along Jurong West Avenue 2, near the contract
boundary with contract J105. The boundary is located at the junction with Jurong West Street 22.

31 August 2023 - A view of the viaduct piers under construction looking eastwards along Jurong
West Avenue 2.

31 August 2023

31 August 2023 - Ongoing installation of sheet piles to create the excavation pit for the pile cap.

31 August 2023 - Work underway for the crosshead construction.

31 August 2023 - The boom of a concrete pump machine visible in the background.

September 2023
At the end of Q3 2023, 

16 September 2023 - Excavation pit for pile cap along the PIE after the line crosses over from
Hong Kah station. This is approximately opposite blocks 408 & 407.

16 September 2023 - Installation of sheet piles to form the excavation pit for the construction of
the pile cap. This is along the PIE, approximately opposite blocks 561B & 559.

16 September 2023 The base of one of the piers now visible along Jurong West Avenue 2 after
turning off the PIE exit ramp. The reception tracks will split off from the main line and cross
over the Choa Chu Kang-bound tracks to swing over to the Tengah Depot.

16 September 2023 - A view of completed viaduct piers along the PIE exit ramp.

16 September 2023 - The base of a new pier visible in the excavation pit.

16 September 2023 - The launch gantry box beam has been assembled.

16 September 2023 - Installation of the first viaduct segments can be seen taking place behind the
launch gantry. These will serve as a starter segment from which the gantry will take over when
installed.

16 September 2023

16 September 2023

16 September 2023 - A view of the ongoing station building works.

16 September 2023

16 September 2023 - A view of the underside of the concourse slab.

16 September 2023

16 September 2023 - A view eastwards of the viaduct construction ongoing.

16 September 2023 - A view eastwards along Jurong West Avenue 2 from street level.

16 September 2023 - A aerial view of the station building construction progress. Scaffolding is
going up at the western end of the station ahead of concourse level column casting.

16 September 2023 - Most of the concourse level slab has now been completed.

16 September 2023 - A view of the viaduct piers with completed crossheads. The installation of
the first few segments can be seen.

16 September 2023 - A view westwards of the ongoing construction.

16 September 2023 - Another view of the station building construction.

16 September 2023 - Crosshead construction underway for the viaduct pier.

16 September 2023 - The first viaduct segments installed and being bonded to the pier.

16 September 2023

16 September 2023 - A view of the lifted segments from street level. The gap between the segment
and the pier crosshead is visible.

16 September 2023 - A view of the remaining viaduct piers with crossheads at various stages of
construction.

16 September 2023 - The base of the viaduct pier for the reception tracks is visible, while sheet
piles have been installed to construct the main line viaduct pier.

16 September 2023

Corporation station is making steady progress, especially when compared to the progress over at its sister station - Hong Kah - across the expressway. The viaduct piers have started to pop up and this should pave the way for speedier construction when the piers are completed and ready for the launch gantry to begin assembling viaduct spans. We look forward to the continued progress and will update on developments in Q4 as we close off the year with a major update. Stay tuned till then!

This post is also available on Instagram & Facebook.

No comments:

Post a Comment