24 January 2021 - View of Choa Chu Kang interchange complex with block 303 demolished

Work on contract J102 has proceeded swiftly with demolition of Block 303 Choa Chu Kang central commencing in December 2020. A month later and the entire block has been brought down to make way for the new Jurong Region Line (JRL) being added to the station complex. As part of the JRL project, two additional platforms will be constructed at the station, allowing access from the North South Line (NSL) to the JRL.


Cross section of Choa Chu Kang interchange
Source: LTA

Screenshot from Facebook on commencement of demolition works

12 January 2021 - A view of block 303 demolition works

12 January 2021 - Close up view of demolition works

24 January 2021 - Close up of demolished block 303

Further along Choa Chu Kang Avenue 3, some works can be noticed such as tree felling and trial trenching works. As time goes on, it is expected that the pace of such works will ramp up further. Additionally, a new hoarded-off site has come up where the line curves to run parallel to the existing NSL tracks.

24 January 2021 - Remains of a felled tree along Choa Chu Kang Ave 3

24 January 2021 - Trial trenching works

24 January 2021 - Hoarding going up at a worksite at the junction of Choa Chu Kang Ave 3 & Way

24 January 2021 - Close up of hoarded up worksite

Land clearing within Tengah New Town has also progressed with a part of formerly forested area being cleared and leveled for upcoming construction. It is likely that an access road will be constructed here for construction vehicles to access sites within Tengah New Town.

24 January 2021 - Land clearing within Tengah New Town

24 January 2021 - Close up of land clearing in Tengah New Town