J112 - Jurong Hill & Jurong Pier update Q3 2023

 

Station work sites under contract J112 as at end-Q3, in September 2023.

We're almost there at the end of our Q3 updates for the Jurong Region Line (JRL). To finish off the phase 3 southern section update, we're at contract J112 which includes the construction of Jurong Hill and Jurong Pier stations. Over the past quarter, some of the permanent structures for the line could be seen emerging. Do head on after the jump to find out more, promise that we'll keep this brief.

JS11 - Jurong Hill
Progress at the site has been focused on preparing the location for major works to come. With the former pedestrian overhead bridge out of the way since Q2, works shifted to preparations for the road diversion to allow more space for equipment to move into the site in the road median. Over the next quarter, we expect piling work to commence proper.

31 August 2023 - A view southwards along Jurong Pier Road from the junction with the Ayer
Rajah Expressway.

31 August 2023 - The road median has been converted into a work site. A road underpass will
be constructed here, with the JRL viaduct running through the road & underpass median.

31 August 2023 - A view southwards of the site of the future Jurong Hill station site.

31 August 2023 - The road median progressively being converted into a work site.

31 August 2023 - A view northwards along Jurong Pier Road, after the Jurong Pier flyover.

31 August 2023 - Preparations underway for an upcoming road diversion.

31 August 2023 - New and old roadways next to each other.

31 August 2023

31 August 2023 - A view of the roadway at the junction with the Ayer Rajah Expressway nears.

28 September 2023 - A view southwards, to Jurong Pier Road, from below the Ayer Rajah
Expressway flyover.

28 September 2023

28 September 2023

28 September 2023

28 September 2023

28 September 2023 - A view of the new northbound roadway, not yet put into use.

28 September 2023

28 September 2023

28 September 2023

28 September 2023

28 September 2023 - A view of the work site in the road median for the underpass and JRL viaduct.

JS12 - Jurong Pier
Over Q3, it was noted that the base of some of the station's pier columns had been cast. The concrete footings and rebar for the upward connections could be seen at the station site. The area where an exit, connected to the station building via an underpass, is to be located was observed to be cleared of vegetation. Further north along Jurong Pier Road, work was also underway for preparation of viaduct pier construction.

31 August 2023 - A view of Jurong Pier Road to the south.

31 August 2023 - Jersey barriers in place near the entry to the Jurong Pier flyover.

31 August 2023 - The slip road from southbound Jurong Pier Road to the junction with Jalan Buroh.

31 August 2023 - A view of Jurong Pier Circus with the station site further in the background.

31 August 2023 - A view of the station work site.

31 August 2023 - The base of some of the station piers visible.

31 August 2023 - A view of the Jurong Pier flyover and the road side table, cleared of vegetation.

31 August 2023 - Cleared vegetation for one of the future exits of the station, to be connected
via a subway.

31 August 2023 - A view of the station site seen from the south along Jurong Pier Road.

31 August 2023 - A view of the station work site behind the hoarding.

31 August 2023 - The base of the first few station columns visible.

31 August 2023 - A close up view of the station column bases with rebar visible at the top.

28 September 2023 - Looking south towards the Jurong Pier flyover.

28 September 2023

28 September 2023

28 September 2023 - Work in progress along the slip road to Jurong Pier Circus & Jalan Buroh.

28 September 2023

28 September 2023

28 September 2023 - A view of the station site from the north.

28 September 2023 - The stumps for the station pier columns visible.

28 September 2023

28 September 2023

28 September 2023 - Soil investigation works taking place near the location of the subway exit.

28 September 2023

28 September 2023 - A soil investigation rig on site.

Works at contract J112 have come some way over Q3 with the station structure at Jurong Pier beginning to emerge. We look forward to viewing the progress made at the contract site in Q4 to come. As we wrap up our JRL Q3 updates with one final post for Phase 3's northern section in NTU, do keep a look out for our year-end update coming soon.

This post will also be available on Instagram and Facebook on 20 December 2023.