J109 - Jurong Town Hall update Q2 2023

 

20 May 2023

While work at contract J109's Jurong Town Hall station site has been progressing, the rate at which it has been doing so is a little slow. Over the past quarter - Q2 of 2023 - there have not been many noticeable differences. We begin our Q2 review of this Jurong Region Line (JRL) station with a look back at the site towards the end of Q1 to jog our memories on how the site looked then.


25 February 2023 - Machinery on site just south of the station area.

25 February 2023 - Casting of the station footings completed, work moves on to the rebar beams.

25 February 2023 - A view of the station area.

25 February 2023 - A view westwards along Jurong Town Hall Road.

25 February 2023

February 2023 (Q1 2023)
Work has progressed mostly at the station area. At the end of 2022, the beginnings of the station were only beginning to become apparent. With the footings completed, rebar installation work has gained some traction with the beams becoming more visible in comparison to the end of last year. Some diversion work has also commenced along Jurong Town Hall as work progresses beyond the station site.

16 April 2023 - Further road diversions in place along Jurong Town Hall Road. This diversion
will facilitate works in the road median.

16 April 2023 - Ongoing works at the station site area.

16 April 2023 - Sheet piles in place for the excavation ahead of pile cap construction.

16 April 2023 - Rebar for the station columns visible.

April 2023 (Q2 2023)
Not too much has differed from Q1 with station construction still focused at street level and road diversions in place along Jurong Town Hall Road. Some progress can be seen just south of the station, where sheet piles have been installed to commence pile cap construction for one of the piers.

20 May 2023 - The base of the pier visible within the sheet piles.

20 May 2023 - Beams have been cast for the station, defining the station's outline further.

20 May 2023 - A close up view of the rebar for the station column.

20 May 2023 - Another view of the road diversion along Jurong Town Hall Road.

20 May 2023 - Construction work in progress at the junction with Jurong East Street 11.

20 May 2023 - Ongoing construction work near one of the ancillary buildings for the
common services trench.

May 2023 (Q2 2023)
Work at the station are has progressed with the casting of the beams at street level, further defining the station outline. At other areas along the contract, work has commenced on sheet piling for utility diversions and pier construction. Some evidence of the progress will become more apparent in time to come.

With works along Jurong Town Hall Road ramping up, it will not be too long before more viaduct piers join those under construction in altering the landscape. Do follow along as we bring you updates on the construction status in time to come.