J105 - Bahar Junction update Q2 2023

 

29 June 2023

Rounding up our update for Phase 1 of the Jurong Region Line (JRL) at Q2 is Bahar Junction station, also under contract J105. Similar with Jurong West station, we had done an update in the early part of the quarter hence this update covers the remaining parts of the quarter of May & June 2023.


7 May 2023 - A view of the station pier columns in the road median
along Jurong West Avenue 4. The Jurong Pier-bound track will sit
on top of this row of columns, above the concourse level.

7 May 2023 - A view of the same row of station pier columns from another angle.

7 May 2023

7 May 2023 - A view of the site towards the junction with Jurong West
Streets 64 & 75.

7 May 2023

7 May 2023 - A station pier column and a viaduct pier column along
Jurong West Avenue 4.

7 May 2023 - Looking northwards at the site along Jurong West Street 64.

7 May 2023

7 May 2023

18 May 2023 - A view northwards along Jurong West Street 64.

18 May 2023 - The base of a station pier column visible in the road median. This will support the
Peng Kang Hill-bound concourse & platform.

18 May 2023 - The base of another station pier column visible. This is noticeably larger to allow
the station to span across the junction without any columns in between.

18 May 2023 - Station pier columns along Jurong West Avenue 4.

18 May 2023

18 May 2023 - Pile cap construction works for a station pier along Jurong West Street 75.

18 May 2023 - Station and viaduct piers along Jurong West Street 75.

28 May 2023 - Bored piling has begun along the eastbound
lanes of Jurong West Avenue 4 to support the Choa Chu Kang-
bound track above the concourse level.

28 May 2023

28 May 2023 - Bored piling in progress for the curve towards
Boon Lay & Jurong Pier.

2 June 2023 - A view of the pier columns along Jurong West Street 75.

2 June 2023 - Station pier columns along Jurong West Street 64.

2 June 2023

2 June 2023

2 June 2023

2 June 2023 - Progress of works along Jurong West Avenue 4.

2 June 2023

2 June 2023

2 June 2023

2 June 2023

11 June 2023 - A view westwards to Bahar Junction station as seen from Jurong West station.

11 June 2023

29 June 2023 - Viaduct pier column with formwork being installed for crosshead construction.

29 June 2023

29 June 2023

29 June 2023 - Two large station pier columns on either side of the junction with Jurong West
Avenue 4 to allow the station to span across.

29 June 2023 - Columns along Jurong West Street 75 with bored piling work underway.

29 June 2023 - A view of piers along Jurong West Street 75 looking southwards.

29 June 2023

29 June 2023 - Piers along Jurong West Street 64.

29 June 2023 - Station piers in the median of Jurong West Avenue 4 wrapped up in construction
netting and scaffolding.

Over the last 2 months of the past quarter, works have picked up pace with several of the station's pier columns coming together. Those along Jurong West Street 75 especially, were pretty quick to be built up to the crown level having only been at the pile cap level several weeks ago. Due to the station's unique T-junction layout, bored piling is progressing on several fronts. For the 90-degree curve from Jurong West Avenue 4 to Street 64, bored piling is underway for the viaduct piers that will help to support that curve.

Also underway is bored piling for the station piers along the northern side of Jurong West Avenue 4, parallel to the eastbound lanes. These will help to support the Choa Chu Kang-bound trackway which sits above the concourse level. As such, the station concourse effectively straddles the eastbound lanes of Avenue 4, while the westbound lanes will remain unobstructed above.

Work is also underway to begin crosshead construction at some of the viaduct piers next to the station. Due to the limited work space and the need for cantilevering, the metal frame used is rather thick to support the heavy loads. We'll bring you more updates on the construction progress at Bahar Junction when available - so do stick around to find out more in due time.

This post will also be available on Instagram & Facebook on 26 July 2023.