J102 - Choa Chu Kang update Q2 2023

 

2 June 2023 - An aerial view of Choa Chu Kang Jurong Region Line (JRL) station work site.

23 March 2023 - A view of the station work site at the end of Q1 2023.

The past quarter has seen the station site at Choa Chu Kang take shape as rebar is installed and concrete poured. More of the station cable troughs and base slab can be seen being built. Installed rebar gives us an idea of where the facilities such as vertical transport and viaduct columns will go. Most of the work has progressed out of foundation works and will transit to the building of the station structure.


2 June 2023 - Existing entrance to the station next to Lot 1 shopping mall.

2 June 2023 - A view of the corridor connecting the MRT and LRT stations in the fare unpaid area.
23 March 2023 - A view of the portal pier foundation excavation pits.

2 June 2023 - The excavation pits for the portal pier have been backfilled.

2 June 2023 - The base stumps of the twin pier columns can be seen.

2 June 2023 - A view of the station site.

2 June 2023 - Form work in place ahead of further rebar installation and
concrete pouring of the cable trough.

2 June 2023 - A close up of rebar columns at the station work site.

2 June 2023 - A caisson pit near the station.

2 June 2023 - Expansion works at the North-South Line (NSL) station.

2 June 2023 - Works on the over run track pier are underway.

2 June 2023

2 June 2023

2 June 2023

2 June 2023 - Rebar for expansion & reconfiguration works at the southern end of the NSL station.

2 June 2023

Works at the station site have revolved around getting the foundations settled and the base slab cast. As part of these works, provisions for electrical wiring, ducts and plumbing have to be made. These come in the form of cable troughs running the length of the station and allow for sufficient space for the installation of these services. Further south, the beginnings of the stumps for viaduct piers can be seen rising upwards. The coming months will see the full fit out of rebar and subsequent casting of the pier columns.

16 April 2023 - Work to cast a diverted drain under way.

16 April 2023 - The diverted drain will allow for the construction
of a viaduct pier column nearby.

16 April 2023 - A view inside the site parallel to the NSL tracks,
with a viaduct pier visible.

Work has also progressed at the site that runs parallel to the NSL tracks. A single viaduct pier stands within the site, a fruit of the long hours of labour put in. Several more will join in over the course of the next few months before crossheads are cast and the viaduct spans go up. Do stay tuned as we bring you further updates on the progress of works here.

This post will also be available on Instagram & Facebook on 19 July 2023.