J103 - Corporation Q1 2023 progress

 

5 February 2023 - An aerial view of the Corporation station site.

Contract J103 was one of the first contracts for the Jurong Region Line (JRL) to be awarded. One of the stations under this contract is Corporation station located next to the site of the former Jurong Junior College. Work on the station has been progressing steadily with crossheads for the station piers being constructed. This will serve to support the station's concourse level via T-beams which will be installed between the crossheads, forming the flooring of the said level.


5 February 2023 - Bored piling works for a viaduct column.

5 February 2023 - A close up view of the station's western end.

5 February 2023 - A close up view of the concourse level crosshead being built.

5 February 2023 - A close up view of the station piers towards the eastern end.

5 February 2023 - The eastern end of the station site.

5 February 2023 - Further piers in progress towards the eastern end.

Corporation station will sit in the road median of Jurong West Avenue 2. Currently, both bounds of the roadway have been diverted to the north to allow for construction work access to take place. It may be possible for the road to be diverted back once again after the construction of the piers in the road median is completed - time will tell if this is the desired construction sequencing for this contract. Meanwhile, views from the adjacent roadway offer a different view of the site.

5 February 2023 - A view from Jurong West Avenue 2 aboard a double decker bus.

5 February 2023

5 February 2023

5 February 2023

The contract also involves the construction of a section of the line that will interface with the depot. A total of 4 trackways leading to 3 reception tracks for the depot will be built alongside the mainline viaduct. A complicated spaghetti-like network of viaducts is thus necessary to allow the line to thread through along the Pan Island Expressway (PIE) while allowing connections to the stations & depots for operation.

5 February 2023 - The mainline will run south of the PIE but the tracks to the depot will begin
crossing over first.

5 February 2023 - The mainline viaduct will hug the canal next to the PIE.

5 February 2023 - A view of the diverted slip road to make way for pier construction.

5 February 2023

12 February 2023 - An aerial view of the diverted slip road connecting the PIE and Jurong
West Avenue 2. Also visible are the excavation pits for bored piles that will support the viaduct
pier.

12 February 2023

12 February 2023

Circulars put up at nearby blocks detail the anticipated upcoming works and their respective timeframes for Q1 of 2023. The scope of works has not changed drastically and still involves excavation, piling & casting works.

12 February 2023

19 February 2023 - An excavation pit with an emerging viaduct pier.

19 February 2023

19 February 2023

19 February 2023

19 February 2023

Work at Corporation station is progressing steadily. We look forward to the time upon which the contract can begin viaduct segment launching works, like neighbouring contracts J105, J106 & J108. Do stay tuned as we update on the progress at the various contracts of the JRL.

This post is also available on Instagram & Facebook.