J110 - A new bus interchange

 

29 November 2020 - A view of the first temporary Jurong East bus interchange next to Jurong East MRT station.

After nearly 9 years in operation, the first temporary bus interchange at Jurong East will be relocated. To our knowledge, this is the first time where a second temporary facility has been constructed for use. Come 6th December 2020, operations will commence at the new facility located opposite the existing interchange. This will be the second bus interchange to shift in order to facilitate construction works for the Jurong Region Line (JRL).

Monday, November 23, 2020

J102 - Progress and upcoming activities

 

14 November 2020 - An aerial view of Choa Chu Kang interchange station site.

Since our last update of Contract J102, there has been some progress made. Most visible is the progress around Choa Chu Kang station for site preparation. Scaffolding has been going up around the vacated Block 303 along Choa Chu Kang Avenue 4. A few fabric noise barriers have been installed ahead of the demoltion works.

Wednesday, November 18, 2020

J107 - It's coming!

14 November 2020 - A view of Jurong West Street 75 and Gek Poh Shopping Centre.

For years my relatives have lived in Gek Poh Ville, right opposite Gek Poh Shopping Centre & Community Club. When I used to stay with them, a ride on bus route 243 was necessary to get to the MRT station at Boon Lay, the then western terminus of the East West Line. Back then the only buildings around Jurong West Central 1 were the Jurong Point shopping centre (albeit much smaller), the MRT station and the bus interchange. Jurong West Street 64 did not even run under the MRT viaducts at that time. From this, you can tell just how long my relatives have been residing in Gek Poh - long enough for my cousins to have progressed from being primary school students to working adults.

Thus it was with much excitement that one of them messaged me some photos of circulars from the contract J107 main contractor that had been put up at the lift lobby of their block - "It's coming!" she texted excitedly. Contract J107 is for the construction of Gek Poh and Tawas stations with associated viaducts for the Jurong Region Line (JRL).

Monday, November 9, 2020

J106 - Upcoming work at Boon Lay

 

08 November 2020 - An aerial view of the Boon Lay East West Line station with the LTA Project office in the background

The site around Boon Lay station has undergone some changes since the update of the site of the future Jurong Region Line (JRL) interchange station. Since our last visit to Contract J106's site, more site offices have sprung up in the vicinity of the Land Transport Authority (LTA) Project Office and the main contractor has also issued a new circular detailing upcoming works.